(Subsequent note in April 2008 : The Office of Fair Trading (OFT) is currently investigating alleged "bid-rigging activities, and in particular cover pricing" as well as "compensation payments" among 112 construction companies (see
http://www.oft.gov.uk/news/press/2008/52-08).
Mansell is one of the companies under investigation (listed number 12 in the OFT's list). Its ultimate holding company, Balfour Beatty is reported to have "co-operated fully" and as a result "to have been granted leniency to reduce any possible fines")
(NB: Mansell is covered in my 3 June 2008 (74 pg) Witness Statement; (4 pg) Main Points)
Mr Brian Gale,
MRICS, stated
under " 2.05 - Tender
procedure " of his 13
December 2002 report that Mansell had
been invited to tender for the works.
As
evidenced by the enclosures attached
by Ms Hathaway, MRICS, Martin
Russell Jones,
to her 15
July 2002 letter, Mansell
opted to NOT tender for the works.
Nearly two years later, in her 26
March 2004 letter Ms
Hathaway wrote to "All Lessees":
"Due
to excessive delays in collecting the
contributions from all lessees we have
to inform you that it has been necessary to
commence renegotiations with the original contractor
and other contractors (NB!!!).
At
the current time the contract administrators
Brian Gale and Associates are in
discussion with the original contractor
and others (NB!!!) to obtain updated
prices for the works.
Once these prices have been obtained we
will write to all lessees again giving
the current cost, the intention being that
the proposed works can be started as soon as
possible..."
In his 2
August 2004 letter, Mr Barrie Martin,
FRICS,
Martin Russell
Jones, wrote that the
"contract
has been awarded to Mansells"
As Mansell was NOT one of the contractors
who tendered against Killby & Gayford (as
stated under point 2, the LVT determination, ref LVT/SC/007/120/02 (ref #992 on the LVT database)
was based
on the Killby & Gayford quote ) -
and never issued a tender - the 'so called'
Section 20 Notice of 2002 has been
invalidated and a new one should have
been issued. (See also on the LVT section # 4 , # 6 , # 7 )
THIS HAS NOT HAPPENED
Consequently, I do not know what works Mansell
tendered for. (Although I can now see some of
the outcome)

|
Mansell and Mr Brian Gale have a most unique way of describing building a penthouse flat "replacing asphalt roof"
(See Mr Brian Gale's description of the works required (2.4MB) i.e. the "defects" he identified and the "remedies" v. the outcome) ( See also Photo gallery ).
Of course, they continued to misrepresent the works actually undertaken, as evidenced by Mr Brian Gale's letter of 19 October 2005
"...Mansells, the contractors undertaking the works.have now completed the external redecoration" .
|
"The external redecoration" ?
How about the construction of
the penthouse flat?
How about the conversion of
flats resulting in the addition of three
other flats?
These works resulted in 39
flats v. 35 flats at the start of the
works . (For evidence of 35 flats
at the start of the works see, for
example, point 7 of the 17
June 2003 LVT report).)
Do Mr Brian Gale and Mansell think
that people are blind?
(NB: In his 2
August 2004 letter, Mr
Barrie Martin, FRICS, also wrote
"At this stage we will not require
further monies from you as the contract
sum of £513,656 (US$905,200) plus
VAT will not at the present time exceed
the original lowest estimate" .
Not only does he not include the VAT amount,
he also does not include the management fees
(which on the original demand was 11%).
I
view this as deception as the addition
of both, actually brings the total to £669,937
(US$1.81 million) - making this just £66,269
(US$116,850), or 9% cheaper than the Killby & Gayford
quote - on which the LVT determination
was based.
In actual fact, the LVT's
view of the "reasonableness" of
the service charge demand of 15
July 2002 led to a reduction of nearly
70% (including the contingency fund) ( See Leasehold Valuation Tribunal # 4 , # 6 , # 7 )
Indeed, the original sum demanded was £736,206 (US$1.3
million). The outcome of the LVT determination
was a reduction of £500,000 (US$882,000)
(including the contingency fund) leaving a sum
that can be demanded of £235,947
(US$416,000) - or 32%
of the original sum demanded
As a new Section 20 Notice was not issued, the
implication of this under the Landlord & Tenant
Act 1985, in particular the statutory instrument
2003 No 1897 which came into force on 31
October 2003, is that of the £6,350 (US11,200)
Steel Services - Martin
Russell Jones have had from me (for nearly two years), they
can only spend £250 (US$440) on Mansell) .
The scaffolding started to be put in place in
the third
week of August 2004. As can be
seen from the Photo
gallery, by 1 May 2006 (photo of the
entrance corridor), the works were
not completed.
(As an aside, as can also be seen from this
pack - and the Photo
gallery - it took
them 11 months to repair the step in
front of my windows that had been broken at
the start of the works).
Evidently, it takes time to build a penthouse
flat, as well as convert flats such that the
35 flats at the start of the works have now grown
to 39
flats .
In addition to the Photo
gallery, consider
the letter from Mansell to inform that
water will be "turned off.for testing and commissioning on 13
June 2005 " i.e. 10 months after
the start of the works).
Consider Ms
Hathaway letter of 16
June 2005
"The refurbishment of the
front entrance is progressing well."
-
against the evidence contained in the Photo
gallery
Back to top