(NOTE: This section is c. 18 pages in length)
(NB: Main events are covered in my 3 June 2008 (74 pg) Witness Statement; (4 pg) Main Points)
Key events about the works including the related
service demands are detailed in:
In my My
Witness Statement (at
19 October 2003)
The home
page to the site
In varying detail in each of my
complaints, and most comprehensively in my
complaint (1MB) against Martin
Russell Jones.
The following covers the sequence
of events - including
extracts from documents (which can all be accessed
by clicking on the date)
31
January 2001 - Letter from Resident H
to leaseholders, following the 25
January 2001 sent by Mr Andrew Ladsky
to leaseholders, in which she wrote: "residents
cannot be charged for building an extra floor"
7
June 2001 - Letter from
Ms Hathaway to leaseholders, which makes fascinating
reading given subsequent events (points of
note are in bold typeface): "Pursuant to
the terms of the head lease and underleases
held on the property, there is an obligation
to carry out works to the property at the relevant
time. These works are now overdue and
it is planned to carry out a programme of refurbishment in
accordance with the terms of the leases on
the building in the near future. It is planned
to commence the external
refurbishment in the Autumn . "
" At present, there is approximately £125,000.00 (US$220,500) in
the Reserve Fund, but in view of the scope
of works required to be carried out it is anticipated
that the sum will be inadequate to meet the
costs. This means that once the Specifications
have been prepared and estimates obtained,
a Landlord & Tenant Act 1985 Notice will
be served on you giving details of the additional
payment required from you. "
13
November 2001 - Renewal of the 18
September 1998 planning application
to build an extra floor for a penthouse flat
21
December 2001 - Ms Hathaway's letter to
leaseholders informing that Brian
Gale & Associates has been
selected to undertake the condition
survey of Jefferson House. (Of course,
sent just before Christmas; a typical
tactic used by landlords to minimise
opposition from lessees) (See Notices
by landlord).
The contractors sent
their proposals to Jefferson House - where
Mr Ladsky resides - rather
than to Martin Russell Jones. (During
the LVT hearing, Mr Brian Gale admitted
having previously done work for Mr
Ladsky)
26
January and 2 February 2002 - My correspondence
to Ms Hathaway highlighting that, while
the appointment stated that it was for "the
preparation of a schedule of works for
the redecoration of the exterior of the block", the
focus of the tender letters (lift, boiler
and roof) lead to the conclusion that the works
are in fact connected with the planning
application (PPO12523) made by KSR
Architects on behalf of Steel Services
on 13
November 2001 for the " erection
of a new residential penthouse apartment
at main roof level ".
Consequently,
any costs associated with building
of the penthouse flat are not the responsibility
of leaseholders.
It became immediately evident that I had exposed
an intended 'scam' as, within days of
sending this correspondence to Ms Hathaway, I
started to suffer on-going harassment and intimidation,
as well as assault from Mr Andrew David Ladsky .
(I cannot prove these. However, I believe
it to be fair comment to say that there
is enough of a case against Mr Ladsky
to add credibility to my 'alleged' accusations - See
sections Police , Head
Residents Association , Notices
by landlord , Nucleus , Elderly
Resident , Other
Residents and My Diary
e.g. 2005 and 2006)
End February 2002 - Mr Brian
Gale completed his condition survey (1.2MB). The works
/ nature of the works detailed in Mr Brian Gale's
specification are so comprehensive that they
amount to a total overhaul of the block. They
include: new roof; new lift; new boiler plant;
new carpet throughout; new doors; new entrance; new
lighting; new area for the porter; total
repainting internal and external; installation
of mechanical ventilation; replacement of some
windows; re-pointing, etc. (Some of the
works required stem from lack of proper maintenance
and upkeep of the block)
26
March 2002 - Letter from Ms Hathaway to
leaseholders: "The
surveyors have indicated that the cost
of works is likely to be in excess of £1
million (US$1.8m) +
VAT and fees. We would stress
that this is a very rough indicative estimate
and should in no way be relied upon as an exact
figure. The tendering contractors may
produce a price which is significantly more
or less than the price indicated
above depending on numerous factors which contractors
take into account when tendering"
Bearing in mind that the works that ought to
be taking place were repairs and maintenance
works, these comments added to my alarm bells.
Either Mr Gale was exceptionally inexperienced,
or Ms Hathaway was preparing the ground in order
to refer back to this letter at a later stage,
along the lines of: "But we did warn you
in March 2002.".
There was also another factor that added to
my suspicions: in the same letter, Ms
Hathaway stated that ".pursuant to the Landlord
and Tenant notice forwarded to you in December
of last year .would inform you that there were
no comments from any tenants in relation thereto
within the prescribed time limit" .
This certainly was not the case. Indeed, in
a letter to me of the same date i.e. 26
March 2002 , Ms Hathaway wrote: ".you
were incidentally the only objector out
of 35 lessees to the appointments" .
Given subsequent events, the following comment
in Ms Hathaway's letter to me of 26
March 2002 must also be noted: "Your
suggestion that the appointment of professional
advisors is in any way connected with any planning
application is incorrect" (See
the Photo gallery section)
15
July 2002 - Letter from Ms Hathaway to
lessees stating a total sum of £736,206
(US$1.3 million) for the "major works" .
(In his tender document of 20
December 2001 Mr Gale stated "We
would undertake the full range of post
contract administration services from
supervision.our fee would be 10% of the contract
sum...happy to undertake role of planning
surpervisor.our fee would be 1% of contract
sum." )
Ms Hathaway states, " Subject to any observations
which we may receive, it is the intention of
Steel Services to instruct Killby and Gayford
to carry out the work" .
Ms Hathaway also states that estimates are attached. In
fact, as can be seen from what she sent, only
the total amount is given for Killby & Gayford - and
very little else for the others.
Hence, contrary to Ms Hathaway's claim, this
letter cannot be considered a Section
20 Notice, as a duly priced specification
had not been made available to leaseholders.
Landlord and Tenant Act 1985 - Section 20 - (4)
(b) - "A notice accompanied by a copy of
the estimates shall be given to each of those
tenants or shall be displayed in one or more
places where it is likely to come to the notice
of all those tenants"
Ms Hathaway also states that the sum quoted "may
be exceeded due either to subsequent changes
in the specifications."
This amounted to the second warning since 26
March 2002 that the costs "may be exceeded" .
17
July 2002 - With her correspondence of
15 July 2002, Ms Hathaway had enclosed an invoice
for "Major works contribution: £14,400 " (US$25,400) (My
1.956% share of the £736,000 (US$1.3
million) stated in her 15 July 2002 letter)
.
7
August 2002 - Barely
three weeks after sending the demand (which
many leaseholders had probably not received
by then because they live overseas), Ms Hathaway
made an application, on behalf of Steel Services,
to the Leasehold
Valuation Tribunal for "determination
of the reasonableness of the global
sum demanded for the works" .
Point 2 of the 17
June 2003 LVT determination states: "The
application concerns major works set
out in a specification prepared by Brian Gale
Associates and priced by Killby & Gayford" .
11
August 2002 - My letter to Ms Hathaway
requesting "A detailed explanation of how
the amount of £14,400.19 you demand from
has been calculated". "A copy - without charge - of
the Schedule of Building Works as duly priced
by the firm of Killby & Gayford - as the
copy left with the porter had not been duly
priced". "An explanation as to why works are
being carried out to the roof given that a
planning application to build an extra floor
for a penthouse flat was granted on 6 February
2002" . I also state that, if changes
are made to the specifications, I expect a
new Section 20 Notice to be issued.
20
August 2002 - Ms Hathaway
wrote to leaseholders "...we have not received
any significant comments from tenants
in relation thereto within the prescribed
time limit consequently Steel Services
are instructing Killby & Gayford; request
payment of the full amount by 16 September " .
This was definitely not the case, as I knew
that other leaseholders had, like me, asked for
more information e.g. Leaseholder G 's
letter of 3
August 2002 to Ms Hathaway stating: "Before
I can agree to the demand that you have made
I need. (1) a detailed breakdown of the figure
of £564,467 (US$995,000) against
the specification"
30
August 2002 - Ms Hathaway's reply to my
11 August letter: " We
are informed that there is no intention
to build the penthouse at the current time. obviously
any major changes would be advised to lessees" . Given
her conduct and that of her client by then,
her 'assurance' did not put my mind at rest.
I was right: when the works started, so did
the construction of the penthouse flat (see
Photo gallery)
3
September 2002 - Letter
from Leaseholder K's solicitors to
Ms Hathaway: "Please provide a breakdown
of the apportionment of the total amount claimed."
16
September 2002 - My letter
to Ms Hathaway pointing out that: "other
than a lump I have not been provided with any
cost information justifying the £14,400.19
demand" (US$25,400) and in which
I also ask "Why is the contingency fund
not used as contribution towards the proposed
building works?"
20
September 2002 - In her
reply, Ms Hathaway totally ignores my letter
of 16 September as she states: " As
other lessees have paid their contribution ,
and it is intended to start work during October,
we have to require payment by return. if payment
is not made now our client, Steel Services. will
instruct solicitors to commence legal
proceedings" .
In addition to the threat of proceedings,
her statement was yet again: a lie as,
two months later, she
filed a claim in West London County
Court against
11 leaseholders representing 14
flats. As can be seen below, she
sent the same letter to other leaseholders
24
September 2002 - Letter
from Leaseholder D to Ms
Hathaway: ".your letter of 20 September
in which you threaten legal proceedings in
the event of not receiving payment from us. as
of this date. have (not) received
the complete data you undertook to provide at
our meeting in your offices on 30 July 2002. This
situation has prevailed despite two further
letters of remind dated 27 August and 9 September"
7
October 2002 - Letter from Mr
Lanny Silverstone , CKFT, to me, received
on 10 October, threatening legal proceedings,
including forfeiture of my lease and of contacting
my mortgage lender unless Martin
Russell Jones has received full payment
from me of the sum demanded by
10:00 a.m. on 14 October 2002 . (A
similar letter was sent to some of the other
leaseholders)
8
October 2002 - Letter from the LVT informing
of Steel Services application and stating that "supporting
documentation is enclosed" . This
is not the case for the majority of the list
of enclosures ticked on the form. Among those
not sent by the LVT are: (1) "A statement
showing how the service charge is made up. (2) "The
evidence, including any reports or other documents
which you want the tribunal to consider in
support of your case"
8
October 2002 - 'Log of
telephone conversation' To: Joan Hathaway,
From: "David Stewart (LVT): "Ms
Hathaway confirmed that the Leaseholders have
already been served with copies of the estimate
and specification."
10
October 2002 - Letter from the LVT to
inform that a pre-trial hearing will take place
on 29 October 2002. (Most interestingly, the
LVT waited two months to
inform leaseholders that Steel Services had
made an application).
17
October 2002 - My reply to CKFT's 7 October
letter stating that I require additional information
before I can agree to the demand. I point to
the terms of my lease and raise the issue of
the contingency fund. I also ask whether CKFT
is aware that Steel Services has made an application
to the LVT.
19
October 2002 - Letter from Leaseholder
M to the LVT: "I was shocked.
This amount far exceeds the total costs
for work in the previous 17 years. I
had several conversations with MRJ requesting
an executive summary of the planned work
such as "description
of work item' 'cost' 'priority. I
never received such summary. I do not
wish to be involved in a lawsuit. Therefore
I have made a funds transfer'" (See
section 'Business
model of the unscrupulous
landlord in 21st century England')
20
October 2002 - Email from Leaseholder
C to the LVT: "The assessment
is excessive to exorbitant. I paid a proportion,
approximately £17,000 (US$30,000) ,
not of my own free will, but because I felt
intimidated and threatened. Steel Services
and MRJ will take legal action if I do not
comply." (Another example in support of
my Business
model in operation in the sector)
21
October 2002 - Letter
from Mr Silverstone, CKFT ignoring
my reasons for not agreeing to payment ,
stating: "We are sure that Martin Russell
Jones will provide you with copies of
such as you are entitled to receive pursuant
to Section 20 of the Landlord and Tenant Act" and reiterates
the threat of issuing proceedings against
me.
Mr
Silverstone also wrote: "We do not
agree with your interpretation of the
lease" .
And, in reply to my 17 October 2002 question: "We
are aware that Steel Services has applied
to the LVT."
Contrast how Mr Lanny Silverstone treats me in his 7 October 2002 and 21 October 2002 letters v. his 21 October 2002 letter to the solicitors acting for another leaseholder: "We note that you have made no proposal on behalf of your client to pay all or part of the interim service charge. We should be grateful if you could clarify whether your client does in fact have any objection to the cost of the major works..."
22
October 2002 - My submission
to the LVT which includes pointing out
that the evidence suggests that Steel
Services does not exist and cannot therefore
pursue an action in the LVT (see BVI
Registration and Owners
identity sections);
asking for assistance in obtaining a
copy of the priced specification
25
October 2002 - Letter from Leaseholder
D to Ms Hathaway: ".I still wish
to receive as a matter of urgency a copy of
the first part of the specification. you are
not correct, I have not received a copy of
part 2. require as a matter of urgency."
26 October 2002 - A new report
is available at the porter's desk in Jefferson
House. Like the previous one, bar costings which,
in total amount to c. £30,000 (US$53,000),
it is unpriced
29
October 2002 - I (with other leaseholders)
attend the pre-trial LVT hearing. During the
hearing, Mr J.C. Sharma JP FRICS, Chair, tells
us, in effect, to not pay the service
charge until the Tribunal has reached a decision - and
it has therefore been implemented .
We (the leaseholders) are each handed a leaflet in
support of this
". a recent Court of Appeal
case ruling (Daejan Properties Limited
v London Leasehold Valuation Tribunal) determined
that LVTs only have the jurisdiction to decide
the reasonableness of disputed service charges that
are still unpaid except under certain
circumstances". ( NB: bold
type face as per the leaflet). (See
LVT section for more detail).
(As can be seen from the directions issued
by the tribunal, Mr Andrew David Ladsky, Ms Joan
Doreen Hathaway and Mr Barrie Martin of Martin
Russell Jones (MRJ), managing agents for the
block, attended the 29 October 2002 pre-trial
LVT hearing)
7
November 2002 - Invitation
from Martin Russell Jones (I received on the
11th) to "All Lessees" to attend a meeting
on 14 November 2002 to, as per "..the Directions
Hearing at the LVT. to try to resolve any queries
that Lessees may have in respect of the major
works.."
12
November 2002 - I reply that " Given
that the LVT has given the Lessees until
26 November to formally communicate to the
Tribunal "each
item of the proposed work that is in
dispute, stating fully the reasons for each
disputed item" as well as our "information
requirements, I consequently view this meeting
as premature - and will not therefore attend.
Once everybody has had the chance to respond
- as per the above - I will then be happy to
meet to discuss i.e. after 26 November. This
is in line with Point 2 of the directions sent
by the Tribunal. I trust that a meeting between
27 November and 15/16 December can be set with
more than just a three-day notice"
25
November 2002 - My letter to LVT: "it
is impossible for me to form a view as
to the reasonableness of the costs as, other
than a lump sum, I have not been provided with
any information on the composition of the costs ".
For the second time now I ask the Tribunal for its assistance in helping me get a copy
of the priced specification
29 November 2002 - Filing
of one claim ( WL
023 537 ) against 11 leaseholders including
myself (and representing 14 flats) in West
London County Court by Ms Joan Hathaway on
behalf of Steel Services and giving Cawdery Kaye Fireman & Taylor as "the
Claimant's solicitors" .
The Particulars
of Claim state, among others that:
"[I] have
failed to pay the service charges. that they
are now due and owing from [me] to
the Claimant." and include a 'Statement
of Truth' signed by Ms
Hathaway which states:
"The
Claimant believes that the facts
stated in this Claim Form are true" .
(Subsequent note: re. Ms Hathaway signing the statement of truth: it amounts to a VERY SERIOUS BREACH of the Civil Procedure Rules - see My Diary 9 March 2007 and West London County Court - Post 2004, point # 23 )
Filing
the claim in court was duplication and abuse
of process since Steel Services had simultaneously
referred all these matters to the LVT and,
of course: leaseholders had very specifically
been told by the LVT to not
pay the service charge demanded, otherwise
the tribunal would not be able to assist. (
See West
London County Court section)
Very clearly, Steel Services counted
on being able to steamroll its application
to the LVT without any opposition and thereby
get the official seal of approval. (See
below Mr Ladsky's comment on 13 March 2003).
1
December 2002 - Ms Hathaway's
fax to the LVT stating: "I understand that
you have already received our experts report
direct"
9
December 2002 - My letter to the Head
of the LVTs informing her that Steel Services
has filed a claim in West London County Court
10
December 2002 - I write to West London
County Court : ".I wish to bring
to your attention the fact the claimant has
brought exactly the same action under the Leasehold
Valuation Tribunal." and add that "I
therefore assume that I do not need to take
further action"
11
December 2002 - Reply form the LVT that "it
is unable to give independent advice. [I] may
wish to consider taking legal advice" (Translation: 'Get
lost!')
13
December 2002 - "Proof
of evidence of landlord's expert witness
(surveyor) Brian Gale" report (delivered to
my flat post 18 December 2002, and hence, after
the deadline set by the LVT ). As
can be seen from the envelop at the back
of the report, the stamp has not been
franked.
16
December 2002 - 'Mr Ladsky style' letter
sent under Ms Hathaway's name. This letter
was posted 2nd class on 17 December. It therefore
arrived after 18 December - hence, in breach
of the deadline set by the LVT). This letter
is in reply to my 25
November 2002 letter to the LVT. It
does not meet any of my information requirements
and, in effect, calls me a liar.
Comparison of this letter with those sent by
Mr Ladsky - under his name / that of 'Steel Services'
- to myself and other leaseholders (e.g. 25
January 2001 and 2
January 2002 ) suggests that he, rather
than Ms Hathaway wrote this letter. (Part
of this letter was also incorporated in Mr
Silverstone, CKFT, letter of 25
June 2003 ).
'Ms Hathaway' states:
"You have indicated that it is impossible
for you to answer the question of whether or
not you dispute any item. We have, on a number
of occasions, provided you with the information
that you have required. we cannot, therefore,
understand why you should be asserting that
you cannot ascertain what the works consist
of. A report.has been available to you for
many months..we have become somewhat frustrated
and are at a loss to understand what comments
you are actually making in relation to the
proposed works.
Aside from value judgments which are wholly
incorrect, we cannot ascertain what you are
complaining of if, in fact, you are complaining
at all. There is no intent to charge residents
twice, nor have any documents been tampered
with.
The price obtained from Killby & Gayford,
we believe to be extremely competitive and
advantageous to the tenants in the block, the
vast majority of whom have paid and
have made no comment whatsoever in relation
to the conduct of the tendering process or
the preparation of documents.
...we and
our clients cannot help but draw the
inevitable conclusion that the correspondence
in which you are consistently latterly
engaging is for the purposes of avoiding
the perfectly reasonable demand for
payment of
the sum due to refurbish the building ".
17
December 2002 - I send another letter
to West
London County Court stating:
" Action to be stayed" ' and
in which I state: "The purpose of
my attached letter of 10 December 2002 was to
report that the same action is being pursued
by the same party in two jurisdictions: (1) yours;
(2) the Leasehold Valuation Tribunal (case LVT/SC/007/120/02).
Consequently, I would like
to suggest that this action through your County
Court be stayed ."
I nonetheless respond to the claim form by sending
my 17
December 2002 defence to the claim in
which I state, among others:
"I deny the claim because no justification
has been provided for the sum demanded. Claimant
already pursuing claim through the London
LVT (LVT/SC/007/120/02) and process already
fairly advanced. The demand does
not comply with the terms of my lease. Part
of my lease is different from that provided
to the County Court"
18
December 2002 - I inform the LVT that
I have not received anything from Martin Russell
Jones and cannot therefore meet the 7 January
2003 deadline set by the LVT
12
January 2003 - My letter to the LVT requesting
that the 5 February 2003 hearing be postponed
as Martin Russell Jones has not provided me
with a copy of the detailed estimates. Hence,
I have been unable to instruct an expert witness
to determine the reasonableness of the cost
of specific remedies and thus determine specific
items of dispute for the trial.
I also
request that the LVT compels Martin
Russell Jones to provide me with the information.
(Letter copied to Ms Hathaway)
12
January 2003 - My letter to Ms Hathaway
stating that, contrary to her claim I have
not been provided with the necessary information
to allow me to get my own expert to review
and hence highlight items of dispute (letter
copied to LVT)
20
January 2003 - Letter from Ms Hathaway
to the LVT stating that:
(1) her clients object to having the hearing
postponed;
(2) I missed the 7 January deadline to which
I had agreed at the 29 October pre-trial hearing;
(3) the documents I "requested have been
available in the porter's room since the original
notice was served and she has in fact inspected
them"
(4) I declined to attend the meeting arranged
for the lessees in November;
(5) at the meeting lessees who wanted a copy
of the detailed breakdown of the estimate bought
one;
(6) "Our clients feel that Miss Dit-Rawé has
had ample time to instruct experts and we would
obviously have assisted them in order to bring
this matter to a close" ;
(7) "The work is becoming more urgent...problems
with the roof, lift and boiler."
22 January 2003 - Letter from
the LVT to me saying that it refuses to postpone
the 5 February 2003 hearing
5 February 2003 - LVT hearing
focused on my application for adjournment. This
was granted
"in the interest of justice" ( point
16, 17
June 2003 )
Under point 14 of its 17
June 2003 report, the LVT captured:
"Ms Hathaway maintained that Ms
Dit-Rawé had seen the specification.
but was unsure as to whether this had
been a priced version" .
(The same damning evidence is found in Mr
Brian Gale's 24 February 2003 report,
under point 2.04: ".the un-priced
or priced Specification.has been. freely available
for all lessees to view" ).
"In the interest of justice" (!!!)
Why had there not been justice before?
Given what I (and other leaseholders) had communicated
to the LVT (see Leasehold
Valuation Tribunal),
Why was it
necessary for me to employ (at a very
high cost) a barrister (plus a solicitor)
to say what I had already said to the Tribunal
on several occasions?
The first day of the substantive hearing was
set for 13
March 2003 .
24 February 2003 - "Expert
Report /Proof of Evidence" Expert
report by Mr Brian Gale to
the LVT.
Sections 2 and 5 of this report can
only be described as 'a pack of lies' .
Also worth noting in his report, Mr
Gale also
states that, at the 14 November 2002 meeting,
leaseholders had the opportunity to get a copy
of the priced specification. By then, four
months had elapsed since the original
demand for payment had been sent - as it was
dated 17 July 2002.
24
February 2003 - "Expert Report prepared
by Mr T Brock acting as Expert witness for
the respondent" i.e. my surveyor
4
March 2003 - Letter from Ms Hathaway to
Mr Brian Gale (which was supplied as part of
the evidence for the tribunal hearings in March-April
2003), stating under point 19
".regarding
the proposed penthouse .although
the planning permission was granted it
was subsequently found that the scheme
was not a viable proposition . there
are no plans to build the penthouse
at the property " (NB!!!!)
13
March 2003 - First day of the substantive
hearing. During the hearing, Mr
Andrew Ladsky (who was a member of
Steel Services party throughout the 4 day LVT
hearing) said to the Panel:
"Will
Ms Rawé pay the £250,000 (US$441,000) of
additional costs that will
be incurred as a result of the delay in the
start of the works due to hearing?"
The
Chair replied that I was perfectly
within my rights to challenge the application
made by Steel Services.
This was captured in the 17
June 2003 LVT report under point
64:
"Although she is in the minority, the Respondent's
legal right to challenge the Applicant's proposal,
as she had done, cannot be fettered"
13
March 2003 - My reply
to Mr Brian Gale's section 2 and 5 of his 24
February 2003 report to the LVT. Reply
handed to the LVT Panel and Steel Services
party on 28 April 2003, third and final day
of the LVT hearing.
Among others, Mr Gale stated that I was, by
then, the only tenant challenging the demand. This
was a lie - as evidenced for example
by Ms McLean's 9
April 2004 letter to my then solicitors
".the landlord has intimated to the LVT
that no other lessee is disputing the service
charges demanded. That is clearly not the case."
14 March 2003 - Second day
of the LVT hearing
(Numerous key events took place with
West London County from this time onwards.
See West London County Court for further
detail)
2
April 2003 - Letter from the LVT confirming
that "The adjourned LVT hearing will continue
as scheduled on 28 April 2003."
7
April 2003 - Letter from
my then solicitors to Ms Hathaway stating: "our
Counsel will be making an Application
for an Order under Section 20 (c) of the Act
in relation to costs not being added to the
service charge".
7
April 2003 - Same letter also sent to
the LVT.
9
April 2003 - Letter from Ms Lisa McLean,
Piper Smith & Basham (then acting for other
leaseholders), to my then solicitors ". we
shall be contending that the county court proceedings
should be stayed pending the outcome of the
Leasehold Valuation Tribunal"
28 April 2003 - Third and
last day of the LVT hearing
17 June 2003 - Date on which
the LVT signed its determination .
Based on my surveyor's assessment of the determination ( * ) ,
the outcome of the LVT determination, in
relation to the original global sum demanded
of £736,206
(US$1.3 million) (£564,467 (US$995,400)
excl. VAT and 11% management fees for Mr
Brian Gale) was:
Amount disallowed by the LVT
because improvements: £169,498
(US$299,000) (£129,958
(US$229,200) excl. VAT and fees) =
23% of the global sum demanded
Amount for which the LVT could
not make a determination due to lack
of specification = £188,784
(US$332,900) (£144,745
(US$255,250) excl. VAT and fees) =
25.6% of the global sum demanded
A view supported by the LVT, considering
the terms of the lease, as well as RICS best
practice, that the reserve fund should be used
as contribution: £141,977 (US$250,400) - or
19.3% of the global sum demanded
Leaving an amount that can be charged of £235,947
(US$416,000) - or 32% of the original sum demanded .
In other words, £500,000
(US$881,700) of
the sum demanded was not considered
as reasonable.
My share of this at 1.956% equals £4,615
(US$8,150) (vs. the £14,400 (US$25,400) originally demanded)
( * ) NB:
(1) This is based on my surveyor's
assessment of the LVT determination - given that
the LVT did not include a summary of the impact
of its determination on the global sum demanded.
(Hence, it failed to perform its remit. See Leasehold
Valuation Tribunal section, including the Head
of the LVTs subsequent refusals to have a summary
included)
(Please note that my surveyor, Mr Brock, LSM
Partners, is a Chartered Surveyor, member
of the RICS. To which I will add: a highly
professional surveyor, with the utmost
level of integrity)
(2) In the £500,000
(US$881,700) I have included £141,000 (US$250,400)
of contingency fund. M y Counsel raised
it as an issue during the hearing as Steel
Services / Martin Russell Jones had not
used it as contribution towards the costs - and
were refusing to do so. (This is captured
under point 34 of the LVT determination).
(Although it eventually used it in case.
See CKFT)
Although the LVT said to not have the jurisdiction
to force Steel Services to use the contingency
fund, considering Clause
2 (2) (e) of the lease (captured under point 59 of the LVT report),
under points 62 the LVT quotes from the RICS
Code.
While, under point 63, it argues that " The
wording of the clause relating to the contingency
fund or reserve fund in the lease is unambiguous. It
refers to costs expenses and outgoings "not
being of an annually recurring nature", and
as such surely envisages the type of works
proposed at the subject property. the Tribunal
considers it inequitable that this fund should
not be used in part to fund the works, and
cannot accept Mr Warwick's (Steel Services)
contention that to divest or reduce the contingency
fund would be "wrong"
Highlights from the LVT report are included,
among others under Brian
Gale and Martin
Russell Jones sections.
Given the events with West
London County Court,
of the numerous points of note, I draw your attention
to the penultimate sentence of point
64 , on page 15 of the 17
June 2003 LVT report:
".the
Respondent and other tenants (NB !!!)
could not be forced to contribute in the
case of improvements and/or works not determined
as reasonable by the Tribunal..."
24
June 2003 - At the West London County
Court hearing, Mr Lanny Silverstone, CKFT,
hands me
(1) " Major
works apportionment 24th June 2002
Revised " produced
by Martin Russell Jones for which,
in my case (and that of other leaseholders),
the original sum demanded has been
reduced by 24.19%;
(2) a " A
Draft Order and Case Summary " which,
among others, state: "Majority of s/c
expenditure approved. Where not approved,
LVT said that because lack of sufficient
detail in specification rather than because
outside scope or not reasonable" .
Mr Silverstone did not provide any supporting
document as to how this reduction was achieved .
In any case, it was way-off the LVT determination
as it disallowed: 23% of the global sum on
the ground that the items were improvements;
a further 26% due to lack of specification.
In addition to this, there was also the issue
of the contingency fund.
17
July 2003 - CKFT send me a 22 page document "Part
III" of the specifications for the works
with "Revised price" written as heading.
In the same correspondence, it also enclosed
a copy of a 17
July 2003 letter to the judge stating,
in relation to my letter of 15
July 2003 to the same judge: "For
current purposes we wish to record the
fact that figures quoted in Ms Rawé's
letter are wrong".
It was very clear to me from the document that
Steel Services had not implemented the
LVT determination. However,
I needed to get 'official proof' of this - given
that the LVT had, (most conveniently for
Steel Services), not included a summary
in its report of the impact of its determination on
the global sum demanded (thereby failing
to perform its remit).
Consequently, I spent another £1,800
(US$3,200) (on top of the £30,000+ (US$52,900)
the LVT had cost me in terms of solicitors, barrister
and surveyor) to get my surveyor to review Steel
Services "revised priced" document
in light of the LVT determination. Yet again,
I was vindicated - as evidenced by the 31
July 2003 assessment by my surveyor,
Mr Brock, LSM Partners.
21
July 2003 - In reply to Mr Silverstone's
letter of 17 July 2003 asking ". the LVT
to make a determination of the specific amount
of the service charge payable by the tenant
of flat 3, Ms Dit-Rawé." , the
LVT wrote:
"It is not the duty
of the Tribunal to assess the particular
contribution payable by any specific tenant
but only to determine the reasonableness ,
or otherwise of the service charges
as a whole to go on the service charge account from
which no doubt you can assess the proportion
for that particular tenant " .
This clearly demonstrates that the LVT views
the calculation of the service charges
payable by individual lessees as being based
on a fixed global sum to which the relevant fixed
percentage share is applied - as the
norm/ understands the terms of the lease as such - which
indeed it is.
Further evidence of this is also found in Ms
McLean's letter of 9
April 2003 to my then solicitors, in which
she captured a voice message from the LVT Clerk:
"I
have had an opportunity of speaking
to the chairperson of the tribunal and she
informs me that what the tribunal is looking
to determine is the reasonableness of the global
figure that's attributable to the whole block"
5
August 2003 - Letter from Ms Hathaway
to 'All lessees' stating: "vast majority
of leaseholders have paid their contribution;
small minority who have not paid and this is
delaying the implementation of the works. Solicitors
acting on behalf of Steel Services are actively
taking action against the lessees"
26
August 2003 - Although I did not
owe a single penny because the demand was not
compliant with the terms of my lease, as well
as being in breach of statutory requirements (defined
under sections
20 and 21 of the Landlord & Tenant
Act 1985), at the hearing in West London County
Court, I agreed to pay the sum of £2,255
(US$4,000) . ( See West
London County Court for reasons)
21 October 2003 - CKFT faxed
a document to Piper Smith & Basham described
as a " Without
Prejudice Claimant's Part 36 Offer " .
It starts by stating,
"Our client maintains
that, as a result of the LVT decision dated
17 June 2003, it is entitled to payment from
your client of the sum of £10,917.27 (US$19,250) ,
as set out in the revised major works apportionment
dated 24 June 2003 issued by Messrs Martin
Russell Jones ".
It then proceeds with accusing
me of having "caused inconvenience
and expense to all the lessees of the
building" because
I "challenged both the LVT decision and
continued to defend these proceedings"
In fact, remaining uncertainties resulted
only from Steel Services failure to supply
the LVT with enough information to take a final
decision on all the issues and, as evidenced
by the statement in the 'offer',
"our client
has once again reviewed the revised
apportionment dated 24 June 2003",
it is Steel Services that kept challenging
the LVT determination. As
it was clearly unhappy with it, it should have
followed the proper channels: appeal to the
Lands Tribunal.
It states the offer as £6,350.85 (US$11,200)
emphasising that it includes allowance from the
contingency fund
"our client is also prepared
notionally to utilise the reserve fund
to reduce the total figure"
This is VERY WRONG.
As implied by the word "notionally" Cawdery Kaye Fireman & Taylor -its
client, Mr Ladsky, and his other puppets,
Martin Russell
Jones, did not do this for
the other leaseholders (See CKFT)
And (in typical style!) demands £143.49
(US$250) of interest.
My surveyor determined that no changes had been
made to the specifications i.e. the LVT's determination
had not been actioned - among others, these should
have included re-tendering for some of the proposed
works. These items amount to £200,000 (US$352,700)
or 26% of the original sum demanded.
My
position, which I repeated on countless
occasions to Ms McLean, Piper
Smith Basham/Watton,
and West
London County Court, was that without
proper specifications and tendering process
I could not determine what - if any of
this amount - I am actually liable for under
the terms of my lease.
Leaving aside the issue about non-compliance
with the terms of my lease and L&T legislation,
the offer represents an overcharge of £1,735
(US$3,100)
It took NINE MONTHS for
me to obtain a consent order - which was endorsed
by Wandsworth County Court on 1
July 2004 .
These amounted to nine
months of hell, which included
my taking back control of my case in
December 2003.
For detail of events see Lawyers,
Courts & LSO section, including
all the sub-sections: Cawdery Kaye
Fireman & Taylor & Law
Society, Piper
Smith & Basham/Watton & Law
Society, Stan
Gallagher & Bar Council, Legal
Services Ombudsman, West
London County Court, Wandsworth
County Court and Lord
Falconer of Thoroton.
26
March 2004 - Letter from
Ms Hathaway to "All Lessees": "Due
to excessive delays in collecting the
contributions from all lessees (*) we have to inform
you that it has been necessary to commence
renegotiations with the original contractor
and other contractors.
...At
the current time the contract administrators
Brian Gale and Associates are in
discussion with the original contractor
and others to obtain updated prices for
the works. Once these prices have been
obtained we will write to all lessees again
giving the current cost, the intention being
that the proposed works can be started as soon
as possible.."
(*) Contrast this with earlier communications : e.g.
- 'Ms Hathaway's letter of 16 December 2002 to me claiming that "the vast majority of the tenants have paid";
- Mr Brian Gale, under point 2.09 of his 24 February 2003 "Expert Witness" report to the LVT: "...4 of the 5 objecting Respondents who attended the Pre-Trial Review on the 29th of October 2002 were now not objecting any further and had agreed to pay, or had paid."
- Under 5.01 - "I would like to draw to the attention of the Tribunal that I am advised by the managing agents that now some 31 of 35 tenants have paid, either in full or substantial contributions toward the cost of the proposed works"
- Under 5.02 - "It would therefore appear. that only one lone tenant continues to make any representation or objection of the 35 tenants"
- Mr Andrew Ladsky in his March 2003 letter to the LVT - captured under point 50 of the LVT report, LVT/SC/007/120/02 determination (ref #992 on the LVT database) "31 or 32 of the 35 tenants have paid their contribution towards the major works..."
In his 14
July 2004 letter to me, Mr
Barrie Martin, FRICS, backs-up the lies
by heading the letter with:
"External
repair and redecoration work plus internal
refurbishment of common parts"
2
August 2004 - Mr Barrie Martin writes
to 'All the Lessees' stating that the contract
has been awarded to Mansells and that
"At
this stage we will not require further monies
from you as the contract sum of £513,656.70 (US$995,300) plus
VAT will not at the present time exceed the
original lowest estimate" .
Not only
does he not include the VAT amount,
he also does not include the management fees
(which on the original demand was 11%).
I view this
as deception as the addition of both,
actually brings the total to £669,937
(US$1.81 million) - making this just £66,269
(US$116,850), or 9% cheaper than the Killby & Gayford
quote - on which the LVT determination
was based.
Mansell was not one of the contractors
who tendered against Killby & Gayford.
There has been no tender from Mansell.
Therefore the 'so
called' Section 20 Notice of 2002 has
been invalidated and a new one should
have been issued. This has not happened.
The evidence is clear: Steel Services
is so intent on making leaseholders pay for
works for which they are not liable that it
has opted to ignore the LVT determination.
It
is also abundantly clear from Barrie
Martin's letter of 2
August 2004 that Steel Services intended
to come back and ask for more money
for 'these
works' at a later stage. Which is
exactly what happened in my case
(see below:
21
October and 16
November 2004) (See also Pridie
Brewster for further detail).
(I am not in contact with other
leaseholders).
The letter from Ms Hathaway dated 26
March 2004 states that they were "commencing
renegotiations with the original contractor
and other contractors." . I have not received
any communication between this letter and that
of 2 August 2004.
The implication of this under the Landlord & Tenant
Act 1985, in particular the statutory instrument
2003 No 1897 which came into force on 31 October
2003, is that of the £6,350 (US$11,200)
Steel Services - Ms Hathaway have had from
me (for nearly two years), they can only spend £250
(US$440) on Mansell. ( I do
not even know what works Mansell has tendered
for ).
4
August 2004 - In his outrageous,
libellous, scurrilous letter to me, Mr
Barrie Martin, Martin Russell Jones, states
that: " [I] refused to pay [my] contribution
and this resulted in the proceedings before
the LVT which of course resulted in the considerable
delay in the commencement of the work" . I am sure that it's the story that he, Ms Hathaway - and their client - Mr Andrew Ladsky - 'fed' to other leaseholders at Jefferson House.
11
August 2004 - My reply to Mr Barrie Martin
3 rd week August 2004 - The
scaffolding started to be put up. This
needs to be viewed in the context of the claims
of "urgency" , "leaking roof" etc.
AND the admission 3.5 years previously
that the works were "overdue" (which
they were):
7
June 2001 letter from Ms Hathaway to 'All
Lessees': " .works are now
overdue and it is planned to carry
out a programme of refurbishment in accordance
with the terms of the leases on the building
in the near future. It is planned to
commence the external refurbishment in
the Autumn..." .
The following must also be noted in Ms
Hathaway's letter: "Pursuant to the terms
of the head lease and underleases...there
is an obligation to carry out works to the
property at the relevant time. These works
are now overdue." .
Hence,
there has been prolonged breach of
the repair covenant by Martin Russell Jones. In
fact, the last major repairs took place more
than 12 years - obviously leading to considerable
deterioration of the block and therefore greater
cost of repair
30
January 2002 email from Ms Hathaway to
me: "particularly bearing in mind
the urgency of some of the required works"
26
March 2002 letter from
Ms Hathaway to me: ". the roof has reached
the end of its useful life and is leaking. The
roof must be attended to as soon as possible . Considerable
work needs to be undertaken to put the
property into a substantial state of repair"
She
also stated in this letter: "We
and the head lessees are simply complying
with our .obligations under the leasehold
interest"
20
January 2003 letter from Ms Hathaway to
the LVT :
"The work is
becoming more urgent as
there are continuing problems with the roof,
lift and boiler. Due to the delay in implementing
them the problem with the roof is now deteriorating
and causing substantial damage to the top flats"
Point 2.03 of Mr
Brian Gale's 13
December 2002 "Expert report" to
the LVT:
"Earlier e-mail copies had been
sent to MRJ by BGA as early as 27th
January 2002 in order that MRJ and their
landlord clients could appreciate the extent
and serious nature of the dilapidations and
disrepair noted"
Point 5.09 of Mr Brian Gale's 24
February 2003 "Expert Report / Evidence
of Proof":
" Jefferson House.has had very
little or significant upgrading or
refurbishment for many years. (!!!) It
is clear, upon its face, that the building
is in dire need of significant works to
bring it up to a more modern standard and a
proper, fit and substantial state of repair"
5
August 2003 letter from Ms Hathaway to 'All
Lessees':
"The vast majority of leaseholders
have paid their contribution in respect
of the works but there is a small minority
who have no paid and this is delaying the implementation
of the works. we will be able to advise
you of a starting date in the near future "
26
March 2004 letter from Ms Hathaway to 'All
Lessees': ".the intention being that the
proposed works can be started as soon
as possible "
(See also the Photo gallery)
The reason for this is that, in spite of the
conduct of West
London County Court and Wandsworth
County Court, Martin Russell Jones's
client evidently wanted to make sure it had closure
with all the leaseholders listed on the claim before
announcing the start of the works.
This was done
on the same day that the last
leaseholder capitulated i.e. 2 August
2004, date of Mr
Barrie Martin's letter to 'All the Lessees'
21
October 2004 - Invoice
from Martin Russell Jones to me for £15,448
(US$27,300) which includes
a 'Brought forward balance, £14,452 " (US$25,500).
There was no explanation whatsoever as
to what the sum refers to i.e. there
was no supporting documentation.
(I had previously
received an invoice from Martin Russell
Jones dated 24
May 2004 that stated "Brought
forward balance, £13,430.50" which,
likewise, provided no explanation
whatsoever)
16
November 2004 - Another invoice followed
from Martin Russell Jones, stating "Brought
forward balance, £15,448 " (US$27,240) - likewise,
with no explanation whatsoever
Please note that, by 23 October 2004: (1) CKFT
had taken payment from me of the sum of £6,350 (US$11,200)
several months previously - as evidenced in its 17
February 2004 letter; (2) I had informed
Ms Hathaway of this in my letter to her dated 31
December 2003 , stating
"I have submitted
to CKFT full and final payment of my share
of the costs for carrying out all the major
works at Jefferson House (£6,350.85).This
was a NatWest cheque #1413. Also for your
information, in the same correspondence sent
to CKFT on 19 December, I also enclosed cheque
NatWest #1414 for £264.04 in full
payment of electricity charges"
I had hoped that by then common sense
would prevail over greed and arrogance which
have been the driving force from Day 1 and
that I would be left in peace.
Fair minded, reasonable visitor to the
site, you would think that somebody with two
brain cells, facing somebody like me - who
had nonetheless paid the sum of £6,350
(US$11,200) that was not due and payable -
would have backed-off.
Such is the profile
of Mr Ladsky et. al. and their aides -
and the extent of their arrogance and
greed... and of their 'justified'
belief in the supporting infrastructure
of surveyors, lawyers, tribunals, courts,
etc.
The message was very loud and clear:
Mr Ladsky et. al. wanted to continue
the fight. They
are clearly intent on ruining me / getting
my flat for next to nothing.
As I could find myself back in court, given
my first-hand experience with West
London County Court, CKFT, as well as with Martin
Russell Jones - I
opted to file a complaint against both, CKFT and Martin
Russell Jones (1MB) with their respective
professional body.
For over a year, from November 2004 until
January 2006, I had no communication
from Martin Russell Jones. At this point,
I received an invoice dated
9 January 2006, this time stating a "Brought
forward balance" of £5,625 (US$9,900).
Yet again, no explanation provided.
I
stress that I have not paid the previous
two invoices. Another invoice followed
in June 2006 stating a " Brought forward
balance" of £8,621 (US$15,200). As
with the prior invoices: no explanation
as to the composition of the sum.
Hence, what is the amount currently hanging
over my head? £15,500 (US$27,300)(?), £14,500 (US$25,600)(?), £5,625 (US$9,900)(?), £8,621 (US$15,200)(?)
or all four combined i.e. £44,246 (US$78,000)?
What else is going to be dropped on
me 'with the compliments of Mr Ladsky et. al.
and their aides'? What will they
think of tomorrow? Sending me an invoice for £20,000
(US$35,000)? And what about the day after tomorrow?
Will they wake up thinking that it would 'be
fun' to send me an invoice for £30,000
(US$53,000)? £40,000 (US$70,500)? £50,000
(US$88,000)? More? (Subsequent note - See Portner and Jaskel and West London County Court - Post 2004 for update )
The £5,625 (US$9,900)
invoice includes, among others, an advanced demand
of £814 (US$1,435) for the first half of
2006. I assume it purports to be based on the "Steel
Services estimated expenditure for year ending
31 December 2006" (I cannot determine how
the sum was arrived at).
Among others, this "estimated expenditure" is FRAUDULENT as,
since 31 January 2006, a superior headlessor, Lavagna
Enterprises Limited has been added, and
controls the last floor. (See Owners
identity and Pridie
Brewster for detail)
The 30
June 2006 invoice represents an increase
of £2,995 (US$5,281) over the 9
January 2006 invoice. As can be seen
from the 30
June pack , my half-yearly service
charge BEFORE the addition of four
new flats , including a penthouse
flat that spans the whole length
and width of the top floor, and BEFORE
the complete overhaul of Jefferson House,
was £680
(US$1,200).
As to CKFT, although acting
solicitors for Steel Services, it is keeping
away from me. Indeed, when, what I consider
to be a bogus 'offer of first refusal'
was sent to me in February 2006, Mr Ladsky
opted to use another one of his cowboy
firm of solicitors, Portner and
Jaskel. (NO, I am not going to say 'allegedly'
as any fair minded, reasonable visitor
to the site will have no difficulty understanding
why I am saying this)
I believe it is fair comment for me to say that this
firm has - with malicious intent - provided
me with false and misleading information in
relation to its 10
February 2006 "notice of disposal
by landlord" - an important legal document. Events
are summarised
in my 30
April 2006 letter to Portner and Jaskel.
(See Notices
by landlord - 10 February 2006
for detail). (Subsequent note: Since 2007, Portner and Jaskel has certainly confirmed my perceptions of it )
Fair minded, reasonable visitor to the site,
please remember that...
THE ROOT CAUSE OF ALL THAT HAS
HAPPENED is due to...
Mr Ladsky et. al. and their aides deciding
that I (and other leaseholders) would
be made to pay for this (2.4MB): the
CONSTRUCTION OF A PENTHOUSE FLAT, ADDITION
OF THREE OTHER FLATS AND RELATED WORKS - FOR
WHICH WE
ARE NOT LIABLE.
(This pack (2.3MB), as well as this pack (1.1MB) contain key evidential documents. As to the pay-off, it is evidenced by the block sale of flats in the latter part of 2006, beginning of 2007 which, of course, are in addition to the sale of the penthouse flat BGL 54 458 for £3.9 million (US$6.9 million) in December 2005, etc.
In October 2007, the selling price was £6,500,000 (US$11.5 millions)

Jefferson House
July 2002 |
|

Jefferson House
September 2005 |
To be more precise:
( PDF
of above diagram - at February 2006)
UNBELIEVABLE! ISN'T IT?
MR ANDREW LADSKY ET. AL., CAWDERY KAYE FIREMAN & TAYLOR, MARTIN
RUSSELL JONES, MR BRIAN GALE, PIPER SMITH BASHAM
AND MR GALLAGHER CAUSED ME TO DEVELOP THIS
WEBSITE.
THIS OUTCOME IS OF THEIR OWN DOING .
Back to top