(NOTE: This section is c. 65 pages in length)
(NB: Mr Gallagher is covered in my 3 June 2008 (74 pg) Witness Statement; (4 pg) Main Points)
As in her 3
October 2003 letter, Ms McLean, Piper
Smith Basham, had suggested that counsel
advice would be required in relation
to the court
action and I did not want the barrister
(who had been selected by Piper Smith
Basham to 'act
for me' at the 26 August 2003 hearing) (West London County Court # 11 , My Diary 26 August 2003 ),
I undertook research that led me to
identify Mr Stan Gallagher.
I made this choice as I had heard that Mr Gallagher
tended to act for lessees (information that proved
to be incorrect). I communicated my choice to
Ms McLean, Piper Smith Basham, on 19
October 2003 .
Two days later, Cawdery Kaye Fireman & Taylor (CKFT) sent the 21
October 2003 'offer'.
From liaising with Piper Smith Basham, Cawdery Kaye Fireman & Taylor
and its client realised that I was prepared to
go to trial over this action: I had written a Witness
Statement and was appointing a barrister. It
is my belief that this triggered the 21
October 2003 'offer'.
It should be noted that the
expectation that I would 'strike a deal' with
'Steel Services' i.e. Mr Ladsky et. al.
had evidently been the game plan all along,
as evidenced by Ms McLean's letter of 4
September 2003 (i.e. from the very beginning
of my relationship with Piper Smith Basham),
" Incidentally (NB
!!!) , I took a call from CKFT
today .but in the event that they wished to
make an offer (NB !!!) I
was, as they well know, obliged to put
it to you (NB !!!) They
intimated that they will make a Part
36 offer (NB
!!!)
This is further evidenced by events with Ms
McLean in relation to my Witness
Statement (Piper
Smith Basham # 7 , # 7.17 ).
To which must be added, among others, the
false claim that I had given my consent
to the reply sent by Mr Twyman to CKFT
on 13 November 2003 (as detailed in
the section on Piper Smith Basham # 4, # 7.13 ,
as well as in My Diary : 14 November 2003 ).
I opted to have Mr Gallagher advise me in relation
to the 'offer'.
Ms McLean, my surveyor, Mr Brock and I met with
Mr Gallagher on 28 October 2003 to discuss the
reply to the 'offer'. Ahead of this meeting,
Ms McLean sent a brief to Mr Gallagher, dated 27
October 2003 .
In this brief, she refers to the 22
August 2003 brief she sent to the barrister
in relation to the 26 August 2003 hearing.
Other documents referred to in the briefs include,
among others, my 17
December 2002 defence to the WL 203537 claim - and Particulars of claim (1.1MB),
my 19
October 2003 Witness Statement,
the 17 June 2003 LVT/SC/007/120/02 determination (ref. #992 on the LVT database) , my surveyor's 31
July 2003 assessment of the
LVT determination.
The subsequent communication I saw from Mr Gallagher
was an email he sent to Mr Twyman at 17h09 on
12 November 2003 and two emails on 13 November
2003: one at 10h12 and
the other sent at 15h32 to
which he had attached the draft
reply and draft consent
order .
If you have read the section on Piper
Smith Basham (and/or My Diary for year 2003),
you already know the events in relation
to the reply to the 'offer'
and that I was extremely dissatisfied with
the approach taken and outcome.
It led
me to take back control of my case in
December 2003 in order to send my own reply to
the 'offer',
dated 19
December 2003 - an action which, very clearly, 'the troops' had not expected me to take (My Diary December 2003 , Piper Smith & Basham # 7.17 and sub-points , CKFT # 6.8 )
Unavoidably, this section on Mr Gallagher duplicates
parts of the Piper Smith Basham section.
Main sections
|
A - My complaint against Mr Gallagher
kick-started the 'reject machinery'
of his trade association i.e.
the Bar Council |
My complaint against Mr Gallagher
is that the reply he wrote to the 'offer',
consisting of a notice
of acceptance and a consent
order did not reflect what
had been agreed at the 28 October
2003 meeting. Also, that he provided unbalanced,
biased advice and misrepresented
events in order to endorse his actions.
As in the case of Piper Smith Basham, my complaint
against Mr Stan Gallagher was motivated by the
need to have a defence if Cawdery Kaye Fireman & Taylor issued proceedings
against me for alleged breach of contract.
Initially, I wrote a complaint to Mr Gallagher
on 20
January 2004 . In his email of 23
January 2004 , Mr Gallagher replied:
"I am also asked by the Bar Council to inform
you that my chambers has its own internal complaints
and disputes resolution procedure.that you
may wish to avail yourself of, either instead
of, or prior to making a complaint to the Bar
Council.In the event that you wish to use the
internal Chambers complaints procedure, your
complain should be addressed in writing to
Andrew Arden QC at the address set out below"
In light of this, I sent to Mr Arden the 20
January 2004 complaint I had sent to Mr Gallagher,
stating in my covering letter of 26
January 2004 "Please, consider the
enclosed letter as having been addressed to
you, rather than to Mr Gallagher" .
Ten weeks later, I had not received
a reply. I knew from the post office
that the letter had been delivered on 27 January
(see 26
January 2004 letter).
It led me to file a complaint against
Mr Gallagher with the Bar Council on 5
April 2004 .
I headed my complaint with
"This is a complaint
against Mr Stan Gallagher of Arden Chambers,
London, for abuse of fiduciary relationship
by giving me biased, unbalanced advice, ignoring
highly material facts and non-compliance with
what had been agreed in relation to a 'Landlord-Tenant' £14,400.19 (US$25,400) service
charge dispute with Steel Services represented
by Cawdery Kaye Fireman & Taylor, solicitors
(CKFT) - with detrimental consequences, including
on my physical and emotional health, as well
as financial position"
It generated a 14
April 2004 letter from Mr Michael
Scott, Complaints Commissioner, Bar Council, to
Arden Chambers asking whether it was going
to deal with my complaint. Mr Scott wrote,
"I
am sorry about any confusing messages Mr Gallagher
received from our offices. I fear it has been
impossible to find out exactly what happened
here but I do not hold Mr Gallagher or Chambers
to blame. In accordance with the Bar
Council's policy, Chambers should consider
a complaint, in the first instance, if made
directly to them.. I would therefore be grateful
if Chambers would now consider this
complaint and let me know the outcome in
due course"
To this letter, Mr Carter, Arden Chambers, replied
on 23
April 2004 that he "would be happy
to deal with my complaint" .
This was followed by a 28
April 2004 letter to me from Mr Scott
"I
am afraid I have not been able to verify
exactly what happened between our offices and
Chambers but I am quite clear that the Bar
Council policy is that Chambers should deal
with a complaint, if made to them, in the first
instance. So, Chambers will now consider your
complaint. If you are not subsequently satisfied,
please return to me"

|
I
concluded from these letters that
the trade association 'machinery'
had been set in motion,
in so far as the Bar Council was
unjustifiably taking the blame
for Arden Chambers not responding
to my complaint after a period
of two months.
Furthermore, in the process, the
Bar Council was 'turning a blind
eye' to one of its members' breach
of the Bar Council Code of Conduct.
So, yet again, I was dealing
with another so called 'regulatory
body' that WAS NOT GOING TO BITE
THE HAND THAT FEEDS IT |
I replied to Mr Scott on 3
May 2004 :
"I do not accept your proposed
course of action for the following reasons:
(1) (Aside from not being my problem), Arden
Chambers were perfectly clear as to the procedure
for handling complaints - as indicated in Mr
Gallagher's email of 23 January 2004.
By writing the letter of complaint
to Arden Chambers and giving them a very generous
amount of time to reply, I have more than amply
complied with your professional body's complaints
guidelines. I therefore now expect your Office
to deal with my complaint now which
includes taking into consideration the fact
that Arden Chambers did not reply to my complaint - contrary
to your professional body's guidance"
In spite of the evidence supplied, Mr
Scott still continued with his 'theme'
in his letter to me of 6
May 2004 :
"Given what you say, I
am perfectly happy to investigate your complaint.
However,
I must say I think it is a
pity, despite your reservations, that Arden
Chambers had not had the opportunity to do
so (possibly due to the misunderstanding
between our offices) especially as I received
a letter agreeing to do so from Mr Carter
dated 4 May.
It might well
have been that they could have given
you satisfaction and, if not, you could then
have come to me, giving you two rungs
of the ladder, so to speak"
Note the ". giving you two rungs of the
ladder, so to speak" - which I
viewed as amounting to coercion .
By then, four months had gone by since I had
filed my complaint with Arden Chambers.
It took
another two months before I received
a reply from Mr Gallagher. Although his
reply is dated 9
June 2004 , I only received it on 3
July 2004. (The delay appears to
have been caused by Piper Smith Basham
as evidenced by the following documents: 25
June 2004 letter from the Bar Council
to PSB; 30
June 2004 reply from Piper Smith
Basham).
The outcome was that it took FIVE MONTHS
for me to receive a reply to my complaint
from Mr Gallagher .
My 29
August 2004 response to Mr Gallagher's
9 June 2004 reply took-up most of my evenings
and weekends in July and August.
During this period, in addition to the fight
I was having with the Law
Society in relation
to my
complaint against Piper Smith Basham,
I was also in battle with Kensington & Chelsea
housing department in relation to getting
the year-end accounts for Jefferson House. (See
Council & LGO,
as well as Document
library).
The outcome was that, contrary to my
initial expectation, I wrote to the Bar
Council on 27
July 2004 that I needed more time
to respond.
In its 17
August 2004 letter, the Bar
Council, had the audacity to write
".it
is in everybody's best interest for
this matter to be resolved quickly" .
As I wrote in my 29
August 2004 reply,
" Evidently, this
view is not shared by Mr Gallagher as it took
5 months for me to get his reply. During this
5 month period from the end of January 2004
to the beginning of July 2004 it would have
been considerably more convenient for me to
deal with Mr Gallagher's reply"
This was followed by a reply from Mr Gallagher
on 11
October 2004 and one from me on 31
October 2004 (with an addendum, dated 2
November 2004 ).
It took a further three
months for the Bar Council
to issue its decision dated 27
January 2005 .
Note the double standard: what
the Bar Council and Mr Gallagher did v.
the Bar Council chasing me for a reply after
six weeks (17
August 2004 letter)
The 27
January 2005 decision from the
Bar Council was:
"Having considered the matter
carefully the Committee was not satisfied
that there is any realistic prospect of
a finding of professional misconduct against
Mr Gallagher or that he provided you with
inadequate professional service when advising
you on the landlord's offer. The complaint
was accordingly dismissed"
It also states, "The Committee however,
may be prepared to look at the matter again
if you have some additional evidence in support
of your complaint which was not included in
the letters you have already sent" .
To this, I replied (point 78, 25
March 2005 ) "Your Office has already
been provided with ample evidence and has opted
to disregard it" .
In its reply, the Bar Council also stated
"Under
the rules, there is no mechanism for you to
appeal this decision.If you are dissatisfied
with the way in which your complaint has been
considered by the Bar Council, you may approach
the LSO."
In light of this, I opted to escalate my complaint
to the Legal Services Ombudsman on 25
March 2005 . In her reply dated 30
August 2005 , the Legal Services
Ombudsman wrote:
"I take the view that
the Bar Council's response to your
complaint namely that you failed
to disclose a sufficient case of professional
misconduct or of inadequate professional
service against Mr Gallagher, was
satisfactory and that their decision to
close their file was justified for the
reasons given in their letter dated 27
January 2005"
(See the end of this section, as well as Legal
Services Ombudsman for further detail)
In light of these two replies, I should
therefore describe the following key
points in my complaint against Mr Gallagher and,
indeed, my one-line summary for this section,
as ' MY
ALLEGED ACCUSATIONS' against Mr Gallagher.
Although I am not a lawyer, I strongly
believe that I have a valid complaint
against Mr Gallagher - and I do not believe
that it requires being a genius to see
it.
Fair minded,
reasonable visitor to the site, even
if, like me, you are not a lawyer, I believe
that, having read the rest of this section
you will agree with my conclusion.
As outlined previously, I had a detailed exchange
of correspondence with Mr Gallagher. My 25
March 2005 reply to the Bar Council provides
a good summary as I comprehensively cross-referenced
my reply to previous correspondences.
Back to main sections
B - Summary of Mr Gallagher's position
Mr Gallagher's position which came to light
in correspondence - post the 28 October 2003
meeting - is summarised below. It is drawn from:
an email he sent to Mr Twyman at 17h09 on
12 November 2003
and two emails on 13 November 2003,
one at 10h12 and
the other sent at 15h32 to
which he had attached the draft
reply and draft consent
order , as well as
his 9
June 2004 initial reply to my complaint
which represents follow-up comments / explanations
for his advice / position / actions.
Introduction - My
evidence in support of my complaint
(1) " The
service charge demand was an "interim
demand" "
(1.1) Mr Gallagher and Ms McLean ignored my lease - as well as the fact that the lease supplied with the claim against me, ref WL 203 537 (1.1MB), is materially different from my lease - amounting to claiming obligations on my part that are false
(1.2) The 15 July 2002 demand positioned as an "interim demand" purports to be a Section 20 Notice. It is NOT as I was not provided with detailed costing at the time of the original demand
(1.3) It was a demand for FULL PAYMENT
(1.4) ...and it was an extortionate demand as the impact of the LVT determination was to reduce the original demand by nearly 70% (includes use of contingency fund)
(1.5) At the earliest, works would have only been completed well into the following year
(1.6 ) The 2001 year-end accounts do not reflect the demand
(1.7) In addition to breaching covenants in my lease, the service charge demand also amounts to a breach of my statutory rights under Section 19(2) of the Landlord and Tenant Act 1985
(2) Consequently,
I did not need to be supplied with the year-end
accounts and, in any case, my asking for
the accounts would "only complicate matters
and jeopardise the prospects of compromising
the claim on realistic terms"
(2.1) Mr Gallagher's position amounts to endorsement of breach of covenant in my lease, and of my statutory rights - under which non-compliance amounts to committing a criminal offence
(2.2) The works were started more than two years after the original demand was sent
(3) I
was in a "very
weak position" as I had "no
technical defence to the claim" :
(a) The
LVT determination was a "mix bag"
(3.a.1) Mr Gallagher was unable to highlight one valid example to substantiate his comment that the determination was "a mix bag" - which, very tellingly, was the only thing he had said about the determination in his 29 page reply
(3.a.2) All that was expected of Mr Gallagher was to recognise the findings from the 17 June 2003 LVT/SC/007/120/02 determination (ref #992 on the LVT database)
(3.a.3) In Mr Gallagher's eyes a reduction of £500,000 (US$882,000) of the global sum demanded (inc. contingency fund) "is not likely to carry much, if any weight on the court proceedings"
(3.a.4) Consider also the horrendous pressure I was put under to accept the 'offer' e.g.
(b) " The
landlord had substantially
complied with the statutory consultation
procedure"
(3.b.1) Mr Gallagher has a rather unique interpretation of Section 20 requirements - and a Lands Tribunal case (which is very similar to mine) supports my view
(c) My
surveyor had "demonstrated" , this then changed
to had "said that the offer could
not be bettered" and that "was
a central point"
(3.c.1) It is NOT true . My surveyor neither stated nor demonstrated this
(d) The "Part
36 Offer" was "not a pre-action
offer"
(3.d.1) I hold the view that the 'offer' fails to meet the requirements defined by Lord Woolf
(3.d.2) Neither Mr Gallagher, nor Mr Twyman provided me with any feedback on identifying this
(e) I
had refused opportunities to strike
a deal ( "not accepted
invitations to attend discussions" )
(3.e.1) As can be seen in the following statement, Mr Gallagher held against me the fact that I was not prepared to make a deal
(3.e.2) Secondly, Mr Gallagher held against me the fact I have strong moral principles that prevented me from being treated differently from the other lessees i.e. striking a deal on terms other than those specified in my lease:
(f) I
had "only paid £2,255" (US$4,000)
(3.f.1) In his accusation Mr Gallagher overlooked the fact that I had paid this amount - even though I did NOT owe it - and, by implication, he held against me the fact that I had obeyed, for as long as I could, the directions given to me by the tribunal
(3.f.2) And Mr Gallagher positions himself as an expert on LVTs - including writing a book...
(g) A "summary
judgement had been entered against
me"
(3.g.1) Yet again, Mr Gallagher overlooked the facts of the case
(4) Given
Mr Gallagher's assessment that I was
in a "very weak position" I
consequently "could not ask Steel
Services to pay for my costs ".
In fact, I should be very grateful that
Steel Services had made me an offer without
costs
(4.1) The threat of the 'costs', combined with an assessment that I was in a "very weak position", became the 'major weapon' at the time of the reply to induce me to accept the 'offer' - as evidenced by the following:
(5) As "the
balance of risks was all against me" , if I did not
accept this "life line" and the matter
proceeded to trial, I would live to repent
/ learn my lesson when "in the likely
event that the defence fails" I would be faced
with a "final bill" and be "reminded
that the disastrous outcome was
in accordance with the original advice
given"
(5.1) My reply included asking: "Was Mr Gallagher acting for me or the other side?"
(6) Mr
Gallagher advised that the offer be "accepted
subject to tweaking"
(7) Mr
Gallagher considered that he had "tweaked
the notice of acceptance" , "reflecting
what had been agreed"
(7.1) The Notice Of Acceptance drafted by Mr Gallagher does not challenge a single statement in the ' offer'
(7.2) Two points which, it was agreed at the 28 October 2003 meeting were not worth mentioning, make-up 50% of the contents of the letter
(8) Mr
Gallagher considered that he had "tweaked
the consent order" , "reflecting
what had been agreed"
(8.1) As demonstrated by the 'black on white' evidence Mr Gallagher did not do this
(9) My overall conclusion on the reply written by Mr Gallagher - and sent by Mr Twyman without my consent - is that, evidently, my 'advisers' did not consider...
(10) My complaint of coercion by Mr Gallagher and Mr Twyman were dismissed by the Bar Council (and the Law Society)
(11) Mr Gallagher could give himself a 'pat on the back' for a 'job well done' as the reply "had been accepted and he could not therefore understand why I refused to endorse it"
(12) Furthermore,
Mr Gallagher knows what he is talking
about as he has "considerable
experience of these types of disputes" ,
including "litigation in LVTs" as he
was "writing a book on this subject
on which he would be pleased to expand"
(13) In
conclusion, Mr Gallagher rejected my
claim of malpractice against him, as
he did not consider himself "guilty
of any professional misconduct"
(14) My complaint that I suffered an enormous
amount of stress, anguish, torment and
distress as a consequence of Mr Gallagher's
actions
(15) Other factors I considered should have
been taken into consideration by Mr Gallagher
'my adviser'
(16) The Bar Council's 27 January 2005 assessment
of my complaint was:
(17) Follow-up events: An amasing display of
U-turns and pirouettes by the Bar Council
and the Legal Services Ombudsman
(18) And the 'PIECE DE RESISTANCE'...
(19) My conclusions
Back
to list
C - My evidence in support of
my complaint
The reminder of this section considers each
of the above points in relation to Mr Gallagher's
position by drawing on the content of the following:
the email he sent to Mr Twyman
at 17h09 on
12 November 2003
the two emails he sent on 13 November
2003, one at 10h12 and
the other sent at 15h32 to
which he had attached the draft notice
of acceptance and draft consent
order
his 9
June 2004 initial reply to my complaint
my 29
August 2004 response to Mr Gallagher's
reply of 9
June 2004 (which had additional supporting appendices )
his response of 11
October 2004
mine of 31
October 2004 ( with, due to an
error, an addendum, dated 2
November 2004 )
my 25
March 2005 reply to the Bar Council's
decision of 27
January 2005
The subsequent exchange of letters (covered
in detail under the Legal
Services Ombudsman section) was:
From the Bar Council, letters of 30
March 2005 and 3
June 2005 and my reply of 22
June 2005
From the LSO, the 1
April 2005 letter and my reply of 2
April 2005 ; letters of 8
April 2005 , 7
July 2005 and the 30
August 2005 decision.
In the first section header in the summary of
my 5
April 2004 complaint against Mr Gallagher
I wrote:
"Giving me incomplete and wrong
advice and not taking the opportunity to
remedy the situation in spite of my highlighting
the shortcoming of the advice / emphasising
the binding nature / relevance of legal documents
(an action which, as the client, I should
not have had to take) - leading me to suffer
a detrimental outcome"
At this point I will add, to the above '
allegedly ' - and let the evidence speak for
itself.
As an introduction, at the 28 October 2003 meeting,
I felt a palpable lack of
support for my case from Mr Gallagher (as well as Ms
McLean who spent
a substantial part of the time focusing
on the negatives - placing strong emphasis
on the potential cost implications of my proceeding
to trial and losing the case - instead of ensuring
that I receive a balanced view.
While I do not recall Mr Gallagher endorsing
Ms McLean's opinion at the time, one of
my ' alleged'
accusations (supported by material evidence)
is that Mr Gallagher subsequently aligned
himself with Piper Smith Basham.
As captured under points 30-32 of my 5
April 2004 complaint, feeling that they
were both forgetting the circumstances of my
case,
"In an attempt to summon support,
I pointed out during the meeting
that I had ended up in this situation through
no fault of my own, other than having asked
the following question: "You want £14,400 (US$25,400) from
me, what are you going to spend it
on?"
I
added that we were in the year 2003,
not medieval times.
Yet, not only was
I put in this situation because I had
dared to ask the question, I had also, as a
result, suffered extensive harassment and intimidation,
as well as assault, resulting in my
being constantly in fear for my life" .
I also stated that, among others, what had happened
was a breach of my Human Rights (Article 8 - "Right to respect for private life"; The First Protocole - Article 1 - "Protection of property". (Ms McLean captured
some of my comments in her 28
October 2003 attendance notes)
In fact, I could have added : "In the process, also committing criminal offences against me under the Protection from Harassment Act 1997 ; Malicious Communications Act 1988"
Back to list
(1) The service charge demand was an "interim
demand"
In her 15
July 2002 covering letter demanding payment
of the sum of £14,000 (US$25,000),
Ms Hathaway, MRICS, Martin
Russell Jones,
wrote that the "sum.may be exceeded due
either to subsequent changes in the specification
or to problems encountered while the
works are in progress"
In the 29
November 2002 Particulars of claim (ref
WL 203537), drawn-up by Cawdery Kaye Fireman & Taylor and filed by Ms
Hathaway, the demand is described as an "interim
payment" .
More than a year later, Mr
Gallagher endorsed
this position at the time of the reply
to the 21
October 2003 'offer' in his 17h09 email,
12 November 2003:
"the claim concerns on
account demands based on pre-estimates
of the cost of the works, rather than on the
actual costs of the works" .
He continued to maintain this position "an
interim demand" (point 5, 9
June 2004 ) and under point 3(1) of his 11
October 2004 reply in which he made
two assertions:
".under the terms of Ms Rawé's lease,
an accountant's certificate is not a condition
precedent to an obligation to pay an interim
charge: the claim against Ms Rawé was
for non-payment of an interim service charge
demand. In this connection I note that,
contrary to what Ms Rawé says, the sum
claimed in the claim against Ms Rawé was
a sum payable as an interim (i.e. on account,
or in advance of the expenditure being incurred)
demand
- the fact that a pre-estimate of the total
cost of the works was demanded does not render
the demand a final demand, rather than an interim
or an account demand". ".under the terms of
Ms Rawé's lease, an accountant's certificate
is not a condition precedent to an obligation
to pay an interim charge."
Back to list
(1.1) Mr Gallagher and Ms McLean ignored my lease - as well as the fact that the lease supplied with the claim against me, ref WL 203537 (1.1MB), is materially different from my lease - amounting to claiming obligations on my part that are false
In a landlord-tenant dispute of this nature,
it is PARAMOUNT to consider the terms of the
lease.
An element of my complaint is that during the
28 October 2003 meeting, Mr Gallagher (and Ms
McLean # 7.8 ) were ignoring the terms of my lease. (My Diary 28 October 2003 )
The first point to note is that Mr
Gallagher (and Piper Smith Basham) ignored
the fact that the lease supplied to
the court with the claim is materially different
from mine on a critical aspect.
The Particulars
of Claim (ref. WL 203 537) (1.1MB) drawn by Cawdery Kaye Fireman & Taylor
and filed in court - under
a Statement of Truth - by
Ms Hathaway...
NOTE in 2007 : See My Diary 9 March 2007 re. the issue under Civil Procedure Rules of the 'Statement of Truth' signed in 2002 by Ms Hathaway, a 'managing agent'
...state
"The Claimant attaches
to these Particulars of Claim (i) a
copy of the lease of flat 23 which contains
covenants in the same terms as all the leases ."
This is NOT the case as:
Clause 2 (2)(c)(i) of the lease 'apparently'
for flat
23 reads "The amount
of Service Charge payable by the
Lessee for each financial year of the
Lessor shall be a fair proportion (to
be determined by and at the sole discretion
of the Lessor)..."
(This is equivalent
to saying: "Give your cheque book
to the lessor who will write himself
a cheque for an amount of his choice".
I find it extremely difficult to
believe that a leaseholder would
agree to such outrageously
unfair contract terms )
My
lease states under Clause (2)(c)(i) " The
amount of the Service Charge payable by the
Lessee for each financial year. shall be calculated
by dividing the aggregate amount of the costs
expenses and outgoings...by the aggregate of
the rateable value (in force at the end of
such year) of all the flats in the Building. and
then multiplying the resultant amount by the
rateable value (in force at the same date)
of the Flat " .
I highlighted this in my 17
December 2002 defence to the claim
"Part
of my lease is different from that supplied
to the County Court"
- of which Mr
Gallagher WAS SUPPLIED with a copy.
(Capturing this in my defence, led
to a 23
January 2003 letter from CKFT requesting
a copy of my lease. I complied with
the request) (CKFT # 6.7 )
I had also highlighted this to Ms McLean in
my 21
August 2003 letter, one of the briefing
documents I wrote at the time of appointing
Piper Smith Basham
"Their claim against
me is part of the same claim against other
lessees - even though my lease is different
from that attached by CKFT to their application
to the Court. They did not have a copy of my
lease when they made the claim. They asked
me for a copy after they saw my defence. Should
not they have had a copy of my
lease before putting the claim through?"
Ms McLean did NOT reply to this (Piper Smith Basham # 7.8 )
I hold the view that Mr Gallagher and Ms McLean have therefore turned a 'blind eye and a deaf ear' to Cawdery Kaye Fireman & Taylor's breach of the Court and Legal Services Act 1990 - Chapter 41- Section 17 - A solicitor has a "duty to ensure the proper and efficient administration of justice" (CKFT # 6.7 )
I give this as example of evidence that, from the start, the game plan was to get me to strike a deal with 'Steel Services'
While Mr Gallagher and Ms McLean claim to be
specialists in landlord-tenant disputes, it was I - the
client - who brought up the need to
consider the terms of my lease. I did this by
taking from my file a copy of the 21
September 2003 letter I sent to Ms McLean,
from which I read some of the extracts. I felt
they were both uneasy at my bringing this up.
Of course, in the same way that this was not picked-up by the Bar Council, it was not picked-up by the Law Society in relation to my 16 March 2004 complaint against Piper Smith Basham and my 20 December 2004 complaint against Cawdery Kaye Fireman & Taylor
Back to list
Mr Gallagher's position is based on:
Clause (2)(2)(h) of my lease "The lessee shall if required by the lessor with every half yearly payment of the rent.pay to the lessor such sum in advance and on account of the service charge as the lessor or its agents shall from time to time specify at its or their discretion to be a fair and reasonable interim payment"
My counter arguments - and evidence in support
- are:
(1.2) The 15
July 2002 demand positioned as an "interim
demand" purports to be a Section 20 Notice.
It is NOT as I was not provided with detailed
costing at the time of the original demand.
Under Section 20 of the Landlord and Tenant
Act 1985, a landlord must consult a leaseholder
for works exceeding £250 (US$440)
in value - and this is done by means of a notice:
"The notice shall describe the works to
be carried out and invite observations on them
and on the estimates."
As I captured under point 8 of my 29
August 2004 reply, "It was not until
36 hours before the LVT hearing on 5 February
2003 - and therefore 7 months after I
received the original demand for payment of £14,400.19 (US$25,400) (dated 17
July 2002 ) - that I was provided with
a priced specification"
The evidence is contained in the 17 June 2003 LVT/SC/007/120/02 determination (ref #992 on the LVT database), under Point 14 -
"Ms
Hathaway (of Martin Russell Jones), on behalf
of the Applicant, resisted the application
for an adjournment. She maintained that Ms
Dit-Rawé had seen the specification
in the porter's room, but was unsure
as to whether this had been a priced version " (point
8, 29
August 2004 )
Point 16 of the LVT report states -
"In
the interest of justice, the Tribunal agreed
to an adjournment." (Point
12, 29
August 2004 )
The same damning evidence is also contained
in Mr Brian
Gale's 24
February 2003 report to the LVT, under
point 2.04: ".the un-priced
or priced Specification.has been. freely
available for all lessees to view" . (Point
46, 25
March 2005 )
(See also LVT # 2 , # 3 , # 8.1.2 , # 8.1.3 , # 10.3 , # 10.5 )
Back to list
(1.3) It was a demand for FULL PAYMENT
The 17
July 2002 demand for £14,400 (US$25,400)
was a demand for full payment, being 1.956%
of the £736,206 (US$1.3 million) demanded
in the 15
July 2002 letter - based on the Killby & Gayford's
overall sum.
While this letter states that "the sum quoted
may be exceeded due either to subsequent
changes in the specification or to problems
encountered while the works are in progress" ,
the 7
August 2002 application by Steel Services-Martin
Russell Jones to the LVT was for "determination
of the reasonableness of the global
sum demanded for the works" (LVT # 4 , # 6 )
The sum quoted by Killby and Gayford referred
to ALL the works.
This contractor responded to the specification
produced by Mr Brian Gale. (Point 24, 29
August 2004 )
The works / nature of the works detailed in
Mr Brian Gale's specification are so comprehensive
that they amount to a total overhaul of the block:
new roof; new lift; new boiler plant; new carpet
throughout; new doors; new entrance; new lighting;
new area for the porter; total repainting
internal and external; installation of
mechanical ventilation; replacement of some windows; re-pointing,
etc.
(Parts of the specification stem
from lack of proper maintenance and upkeep of
the block over a period of 12 years - and therefore
in breach of the lease) (point 24, 29
August 2004 )
The LVT's remit is captured under point 2 of
its 17 June 2003 LVT/SC/007/120/02 report
" the application
concerns major works set out in a specification
prepared by Brian Gale Associates and priced
by Killby & Gayford" (point
24, 29
August 2004 )
And further confirmation that the LVT's remit
was to consider the GLOBAL SUM for the
works , is also found in:
The LVT's 29
October 2002 pre-trial hearing directions
The LVT's reply 21
July 2003 to Mr Silverstone, CKFT, letter
of 17
July 2003
"It is not the duty
of the Tribunal to assess the particular
contribution payable by any specific tenant
but only to determine the reasonableness,
or otherwise of the service charges as a
whole to go on the service charge account from
which no doubt you can assess the
proportion for that particular tenant"
This led Mr Silverstone to reply
on 21
July 2003
"We are mindful of the fact that the LVT
was, in fact, in a position to make a determination
of the sums that it considered to be reasonable
based on the evidence that it received at various
hearings"
Ms McLean's letter of 9
April 2003 to my then solicitors, in which
she captured a voice message from the LVT Clerk:
"I
have had an opportunity of speaking
to the chairperson of the tribunal and she
informs me that what the tribunal is looking to
determine is the reasonableness
of the global figure that's attributable to
the whole block" (NB: My highlights)
And Mr Andrew Ladsky and
his 'puppets' were
fully knowledgeable of this, as evidenced by
the following:
The letter that Mr Andrew
Ladsky wrote to the tribunal, which
is captured under point 50 of the LVT
report :
"Whilst I accept that the Tribunal
is to rule on the reasonableness
of the proposed works."
The 16
December 2002 letter to me, sent under
the name of Ms Hathaway (but I believe to have
been written by Mr Andrew Ladsky )
is also quite clear on this point:
". the Chairman of the tribunal's instructions
where he indicated that the tribunal
was concerned with the reasonableness of service
charges as set out in Section 19 of
the Landlord & Tenant Act 1985"
In her 20
August 2002 letter Ms Hathaway asks that:
"[I] make payment. by 16 September so that
the funds are in hand to cover the cost of
the work." .
This "payment" is the sum of £14,400 (US$25,400) - which
is 1.956% of £736,206
(US$1.3 million)
Among others, the list of the percentage contribution for each flat was attached to the 7 August 2002 application to the tribunal.
Back to list
(1.4) ...and it was an extortionate demand as the
impact of the LVT determination was to
reduce the original demand by nearly 70%
(includes use of contingency fund)
As evidenced by the LVT report, the 15
July 2002 demand was highly unreasonable:
Based on my surveyor's
assessment (as the LVT failed
to provide a 'global' assessment, thereby failing
to perform its remit ),
the outcome of the LVT determination,
in relation to the original global sum demanded
of £736,206
(US$1.3 million) (£564,467 (US$995,400)
excl. VAT and 11% management fees) was:
Amount disallowed by the LVT
because improvements: £169,498
(US$299,000) (£129,958
(US$229,200) excl. VAT and fees) = 23% of
the global sum demanded (point 48, 29
August 2004 )
Amount for which the LVT could
not make a determination due to lack
of specification = £188,784
(US$333,000) (£144,745
(US$255,300) excl. VAT and fees) = 25.6% of
the global sum demanded (point 48, 29
August 2004 )
A view supported by the LVT (*) ,
considering the terms of the lease, as
well as RICS best practice, that the reserve
fund should be used as contribution: £141,977 (US$250,000) - or 19.3% of
the global sum demanded (point 48, 29
August 2004 )
Leaving an amount that can be charged of £235,947
(US$416,000) - or 32% of the original sum demanded .
In other words, £500,000
(US$882,000) of
the sum demanded was not considered
as reasonable . (point 48, 29
August 2004 )
See also section on Mr Brian Gale which contains extracts from the LVT determination
(*) In the £500,000 (US$882,000)
I have included £141,977 (US$250,400) of
contingency fund. My then Counsel raised
it as an issue during the hearing as Steel
Services / Martin Russell Jones had not
used it as contribution towards the costs - and
were refusing to do so, in spite of, among
others, having stated this in the 7
June 2001 letter. (This is captured under
point 34 of the LVT determination).
(But
it subsequently did in my case - see the 21
October 2003 'offer'. I believe this
to be because, among others, I had
the 7 June 2001 letter from Ms Hathaway) (CKFT # 6.3 )
Although the LVT said to not have the jurisdiction
to force Steel Services to use the contingency
fund, considering Clause
2 (2)(e) of the lease (captured
under point 59 of the LVT report), under points
62 the LVT quotes from the RICS Code.
Surely,
this report makes it abundantly clear that
further demands for the major works would be
totally unjustified.
It was a demand for FULL payment - and a highly
extortionate one at that.
Back to list
(1.5) At the earliest, works would have only been
completed well into the following year
The works would have been taking place beyond
June 2003, time by which, under the terms of
my lease and of Section 21(4) of the Landlord & Tenant
Act 1985, Steel Services had to issue
the year-end accounts given that the
year-end for Jefferson House is December.
Under points 24 and 25 of my 29
August 2004 I provided an explanation
in support of my claim that the works would
not have been completed before June 2003.
This included the fact that the application
to the LVT was filed by Ms Hathaway
on 7
August 2002 . (Hence, barely
three weeks after the 15
July 2002 demand which many leaseholders
would probably have not received by then
due to living overseas / the holiday period.
It also means that, when Ms Hathaway sent
her 20
August 2002 letter to the leaseholders
stating a start date of "early October" - the
application had by then been filed just seven
working days previously).
In filing the application, Steel Services was,
in my opinion, relying on being able to 'steamroll'
the application through the LVT with little opposition
(in part because many leaseholders live overseas)
and thereby get the 'official' seal of approval.
(Evidence in support of this is the fact that
the claim, WL 203 537, was filed in West
London County Court exactly one
month after the LVT had told us,
i.e. the leaseholders, at the 29
October 2002 pre-trial hearing, to NOT
pay the service charge
until the tribunal had issued its
determination and it had therefore
been implemented). (The LVT signed its
report seven
months later , on 17
June 2003 )
However, even if Steel Services had succeeded
in 'steamrolling' its application, the earliest
at which it could have obtained its 'official
seal of approval' would have been in Q1 / early
Q2 - of 2003 i.e. after the year-end for the
accounts.
As it turned out, my position on the
duration of the works has been amply
vindicated given
that the works were started in August
2004 and were still taking place in May
2006 i.e. nearly two years
after being started - and therefore FOUR
YEARS AFTER THE ORIGINAL DEMAND - as
can be seen from the photos of the corridor
taken on 1
May 2006 .
See also Photo
gallery for
other evidence on the duration of
the works, including broken
step (1.6MB), filth
around my flat , floor
of the entrance corridor (not
to mention the lack of concern
about health & safety )
Under point 3(1) of his 11
October 2004 reply Mr Gallagher wrote
"As
Ms Rawé notes in her response, the works
had not been completed when the LVT made its
determination. Consequently, I remain of the
view that there was no viable contractual defence
to the claim against Ms Rawé"
I pointed out (point 6, 31
October 2004 )
"Correction: the works
had not started. They were started
14 months later (only once Steel Services
had achieved closure on the court proceedings
against the 11 residents)"
Mr Gallagher
knew that the works had NOT been started .
Indeed, he captured this under point
29(6), 9
June 2004 - "(my) surveyor and (I) had
expressed concern that the major
works (which at that stage remained
outstanding)."
(Regarding the latter part of my reply: the
last leaseholder 'capitulated' on 2
August 2004 . On the same
day , Mr Barrie Martin, FRICS,
Martin
Russell Jones, announced the appointment
of a new contractor, Mansell, and the
start of the works).
Back
to list
(1.6 ) The 2001 year-end accounts do not reflect
the demand
In her 7
June 2001 letter to "All Lessees" Ms Hathaway
had written: "It is planned to commence
the internal refurbishment in the Autumn (i.e.
of 2001) with the external refurbishment
to follow on next Spring" .
In her 3
October 2003 letter, Ms McLean wrote, "I
agree that the 2001 accounts do no include
future costs..In any event we have not yet
received the accounts for the year 2002 and
no doubt we can address that situation as and
when it arises"
My lease may be a bit of a hard read in some
parts, but it does not require a PhD to understand
it - including the sections which I view as relevant.
In fact, these are quite clear and easy to understand. My
lease states (point 26, 29
August 2004 ):
Clause 2(2)(d) "As soon as
practicable after the end of each financial
year. the lessor shall cause the amount of
the service charge payable by the lessee for
such financial year to be determined by an
accountant."
Clause 2(2)(e) ". the costs
expenses and outgoings incurred by the lessor
during the relevant financial year of the lessor
shall be deemed to include not only the costs
expenses and outgoings which have been actually
disbursed incurred or made by the lessor during
the relevant year.
but also the sum or sums (hereinafter
called the 'contingency payment) on account
of any other costs expenses and outgoings (not
being of an annually recurring nature) which
the lessor shall have incurred at any time
prior to the commencement of the relevant financial
year or shall expect to incur at any time after
the end of the relevant financial year .
as
the accountant may in his reasonable
discretion consider it reasonable to include
(whether by way of amortization of costs
expenses and outgoings already incurred or
by way of provision for expected future costs
expenses and outgoings) in the amount of
the service charge for the relevant financial
year"
Clause 2(2)(f) "As soon as
the accountant shall have determined the amount
of the service charge payable by the lessee
for the relevant financial year.
the accountant
shall prepare a written statement
containing a summary of the costs expenses
and outgoings incurred by the lessor during
the relevant financial year together with any future
sums indicated by the accountant
pursuant to Clause 2(2)(e).. and specifying
the amount of the service charge payable by
the lessee.
and in the accountant's certificate,
shall certify. that the sum specified as aforesaid
represents the amount of the service charge
payable by the lessee.. "
The demand of £14,400 (US$25,400) was
dated 17
July 2002 (and the covering letter, 15
July 2002 ).
As can be seen from the 2001
year-end accounts for Jefferson
House, they do NOT include
costs the lessor "shall expect to incur at
any time after the end of the relevant
financial year. by way of provision for
expected future costs expenses and outgoings." (points
30 and 123, 29
August 2004 )
In addition (as I captured under point 49 of
my 29
August 2004 reply to Mr Gallagher):
'Even if' lawyers want to argue that the
sum demanded is an "interim payment" (although
I simply cannot see how this could be demonstrated
in view of the facts), I would like to draw
the attention to:
Clause (2(2)(j) of my
lease (attached) ". nothing
shall disable the Lessor from maintaining
an action against the Lessee in respect
of non-payment of any such interim payment
as aforesaid notwithstanding that the Accountant's
Certificate had not been furnished to the
Tenant at the time such action was commenced subject
nevertheless to the Lessor establishing
in such action that the interim payment
demanded and unpaid was of a fair and reasonable
amount having regard to the amount of the
Service Charge ultimately payable by the
Lessee"
Consider this in the context of the fact
that the original demand I received was £14,400.19 (US$25,400) while
the impact of the LVT determination meant that
it should be reduced by nearly 70% to £4,615" (US$8,135)
(Ms
Hathaway filed a claim (WL 203537) (1.1MB) against me in West
London County Court for £14,400 (US$25,400).
The impact of the 17 June 2003 LVT/SC/007/120/02 determination (ref #992 on the LVT database) reduced
the sum to £4,615 (US$8,135).
Hence, in filing the claim under
a ' Statement
of Truth ' Ms
Hathaway and
Cawdery Kaye Fireman & Taylor who produced the claim - breached
Clause (2)(2)(j) of my
lease)
In addition, I also draw your attention to:
Clause 2(2)(c)(ii) of my
lease which states "The lessor
will use its best endeavours to maintain
the annual service charge at the lowest reasonable
figure consistent with the due performance
and observance of its obligations"
(NB: I highlighted this clause in my 21
August 2003 letter to McLean "This
is an important point as clause 2(2)(c)(ii)
of my lease provides that the landlord must
use its "best endeavours" to keep the annual
service charge at the "lowest reasonable figure" )
And, of course, to this must be added the fact
that Steel Services made me an ' offer '
of £6,350 (US$11,200) (+ interest !)

|
In light
of the above, I hold the view that
Martin Russell Jones , CKFT , Piper
Smith Basham and Mr Stan Gallagher
insistence that the demand was an "interim
demand" can only be interpreted
as...
...a shared understanding
between them that another demand
for the "major works" would
be sent to leaseholders - which
is exactly what happened in my
case. |
Consider as well - as can be seen in the transcript of
the 28 May 2004 West London County Court hearing - the comment Ms
Ayesha Salim, CKFT, made about me
"The consent order that she submitted has
included works that may possibly take
place in the future to the property and
not just the amount that is claimed within
this claim " .
'Helpfully', the judge then offered to have
the action against me 'stayed' (open to further
proceedings) - as can be seen in the court
order of that date. (See Lord
Falconer of Thoroton # 3 , # 4)
Back to list
(1.7) In addition to breaching covenants in my lease, the service charge demand also amounts to a breach of my statutory rights under Section 19(2) of the Landlord and Tenant Act 1985
Section 19(2) of the Landlord & Tenant Act 1985 states:
"Where a service charge is payable before the relevant costs are incurred, no greater amount than is reasonable is so payable"
Mr Gallagher, the "property expert" did not take into consideration this breach of my rights when he wrote the reply to the 'offer'. WHY NOT?
Considering the decision of the Bar
Council - and of the Legal Services Ombudsman
- fair minded, reasonable visitor to the site,
do you see why I stated in the introduction
to the site that there is 'no avenue open to
me for justice and redress on this island'?
Back
to list
(2) Consequently, I did not need to be supplied
with the year-end accounts and, in any case,
my asking for the accounts would "only complicate
matters and jeopardise the prospects of compromising
the claim on realistic terms"
Subsequent note: In - my non-lawyer opinion - I hold the view that Mr Stan Gallagher (and Mr Richard Twyman, Piper Smith Basham/Watton) have committed offences against me under: the Malicious Communications Act 1988 and the Protection from Harassment 1997
Opting to endorse Steel Services-Martin Russell
Jones's positioning of the service demand as
an "interim demand" Mr Gallagher
consequently dismissed my request to be provided
with the 2002 accounts because
"Similarly, adding conditions for the
disclosure of the accounts can only complicate
matters further and jeopardise the prospects
of compromising the claim on realistic terms" (17h09 email,
12 November 2003).
He continues,
"Moreover, the terms of response
that Ms Rawé sets out in her faxes
do not constitute a realistic basis
for settling the claim and will not
be accepted by the Claimant. (NB:
Oh dear! Let's not be vexatious to
a sacrosanct landlord! i.e. Mr Andrew Ladsky)
I
must advise that I cannot see the
point of responding in those terms. By this
I do not mean to be unkind, but it must be
remembered that the point of making an offer
is not to debate the issues in dispute, but
to set out a realistic basis to compromise
the claim and (if the claim is not settled)
to protect the litigant's position on costs (NB: 'the
costs!' the favoured weapon!)" (10h12 email,
13 November 2003)
As detailed above, contrary to the terms of
my lease, the original demand was NOT reflected
in the 2001
accounts i.e. they do not include "costs
the lessor shall expect to incur at any time
after the end of the relevant financial year by
way of provision for expected future costs
expenses and outgoings." .
Yet, in her 7
June 2001 letter to "All Lessees" Ms Hathaway, Martin Russell Jones,
had stated an intention "to start the works
in the Autumn" (This intended future
expenditure was not reflected
in the 2000
year-end accounts )
In addition to the clauses in my
lease detailed earlier on, I also draw
attention to the following:
Clause 2(2)(b) "..financial year means
the financial year of the lessor for
which the amount of the service charge
is being determined" (the
year-end for Jefferson House is 31
December)
Clause 2(2)(f) "As soon as the accountant
shall have determined the amount of the service
charge payable by the lessee for the relevant
financial year .
the accountant
shall prepare a written statement
containing a summary of the costs expenses
and outgoings incurred by the lessor during
the relevant financial year together with any
future sums indicated by the
accountant pursuant to Clause 2 (2)(e)..
and specifying
the amount of the service charge payable
by the lessee .and in the accountant's
certificate, shall certify:
"that in his opinion the said summary represents
a fair summary of the said costs and outgoings
set out in a way which shows how they are or
will be reflected in the service charge"
Clause 2(2)(g)(i) "As soon as practicable after
the end of each financial year the
lessor shall furnish to the lessee an account
of the service charge payable by the lessee
for such financial year together
with a copy of the accountant's certificate ."
(see Pridie Brewster, the 'accountant' for Jefferson House )
In her 3
October 2003 letter, Ms McLean wrote,
"I
agree that the 2001 accounts do no include
future costs..In any event we have not yet
received the accounts for the year
2002 and no doubt we can address that situation
as and when it arises"
In light of this attitude, I sent a 9
October 2003 letter to Martin Russell
Jones requesting the accounts - IN
VAIN ! (Martin Russell Jones # 37 ) (I finally obtained a copy two years later - of course after more battles: this time with Kensington & Chelsea Housing and the Local Government Ombudsman )
Back to list
(2.1) Mr Gallagher's position amounts to endorsement of breach of covenant in my lease, and of my statutory rights - under which non-compliance amounts to committing a criminal offence.
Subsequent note: In - my non-lawyer opinion - I hold the view that Mr Stan Gallagher (and Mr Richard Twyman, Piper Smith Basham/Watton) have committed offences against me under: the Malicious Communications Act 1988 and the Protection from Harassment 1997
(Aside from the fact that the demand was in
breach of the terms of my lease), one year
three months had passed since the original
demand.
I HAD to be issued with the year-end
accounts,
not only under the terms of my lease,
but also, as emphasised by Kensington & Chelsea
Housing to Martin Russell Jones in its 25
June 2004 Section 21(1) request, Landlord & Tenant Act 1985.
The letter also highlights Section
25 of the Act that non-performance
results in committing a criminal offence .
As I captured under point 3 of my 31
October 2004 reply to Mr Gallagher, he
knew that the 2001 accounts did not include "provision
for expected future costs expenses and outgoings" - and
also knew that - 10 months after the year-end
- I had not received the accounts for 2002.
Yet in his email of 13
November 2003 , he described my request
(in my 7
November 2003 fax) as
".similarly
adding conditions for the disclosure of accounts
and details of trust fund arrangements can
only complicate matters further and jeopardise
the prospects of compromising the claim on
realistic terms."
In reply to my complaint that I should have
been provided with the accounts, and that in
the Notice
of Acceptance written by Mr Gallagher,
the only reference made to the terms of my
lease reads
"The absence of due compliance
with the service charge certification provisions
prescribed by the lease",
Mr Gallagher
wrote
"the more vaguely this argument
is presented, the better" ( point
55, 9
June 2004 )
My reply to Mr Gallagher was: "For
whom?" (point 123, 29
August 2004 )
To which I will now add : WHY DID MR GALLAGHER TAKE THIS POSITION?
And likewise: why did Piper Smith Basham endorse it? (PSB # 7.9 )
(NB: I finally obtained a copy of the 2002
accounts in February 2005 (i.e. three
year later!) through the intermediary
of the
Local
Government Ombudsman. The
accountants, Pridie & Brewster,
certified the 2002 accounts stating " that
the attached schedule of costs, expenses
and outgoings is sufficiently supported
by receipts and other documents". I
consider this to be incorrect
(See Pridie
Brewster for further detail - including # 18 for what I discovered subsequently: 9 out of the 14 flats on the claim were made to pay the full amount )
As I continued arguing the point, under point
3(3) of his 11
October 2004 reply, Mr Gallagher wrote:
"landlord's
apparent breaches of the service charge accounting are
not matters that negate a contractual obligation
to pay service charges."
The first point to make about this is that I
(and the other leaseholders) had specifically
been told at the 29 October 2002 LVT pre-trial
hearing to NOT PAY the service
charge - as evidenced by page
5 of the booklet that we were handed at
the time (the Court of Appeal case, Daejan
Properties v. LVT)
That aside, I find this statement
shocking and view it as an endorsement of abuse of my most basic rights (in addition to the endorsement of breach of covenants in my lease, and of my statutory rights).
Under point 68 of my 25
March 2005 reply to the Bar Council, I
wrote
"In Mr Gallagher's book, landlords have
carte blanche to do exactly as they please - including
incorrectly referring to a demand as an interim
payment and issuing action for non-payment,
as well as subsequently making another demand
(the offer) - also in breach of the terms of
my lease.
The outcome of Mr Gallagher's position
is that the contract i.e. the lease
- signed by the landlord and the lessee -
works in only one direction: that of the
landlord.
Bar Council Code of Conduct - 303. "A barrister:
(a) must promote and protect fearlessly
and by all proper and lawful means the lay
client's best interests and do so without regard
to his own interests or to any consequences
to himself or to any other person (including
any professional client or other intermediary
or another barrister)
(b) owes his primary duty as between
the lay client and any professional client
or other intermediary to the lay client and
must not permit the intermediary to limit his
discretion as to how the interests of the lay
client can best be served"
Bar Council Code of Conduct - "5. Conduct
of work: 5.2 A barrister must
assist the Court in the administration of justice
and, as part of this obligation.must not deceive
or knowingly or recklessly mislead the Court"
Under point 26 I wrote
"While Mr Gallagher
opted to ignore the fact that the lease supplied
with the claim against me is materially different
from mine (as it amounts to saying: "Give your
cheque book to the lessor who will write himself
a cheque for an amount of his choice"), it
still does not change the terms of
my lease"
While under point 40, I captured "Your Committee
has opted to ignore the fact that this exorbitant
service charge demand was in breach of the
terms of my lease e.g. Clause 2 (2) ( c) (ii) which
states Lessor's duty to " maintain
the annual service charge at the lowest reasonable
figure consistent with the due performance
and observance of its obligation herein" .."
As detailed in the previous section, under point
3(1) of his 11
October 2004 reply Mr Gallagher wrote "As
Ms Rawé notes in her response, the works
had not been completed when the LVT made its
determination. Consequently, I remain of the
view that there was no viable contractual defence
to the claim against Ms Rawé"
Back to list
(2.2) The works were started more than two
years after the original demand was sent
The works were started only once Mr Ladsky et. al. had secured closure
in the courts with the last valiant leaseholder.
As can be seen, the Wandsworth
County Court order is dated 2
August 2004 . On
the same date, i.e. 2
August 2004, Mr
Barrie Martin, FRICS,
sent a letter announcing the start of
the works.
The 'so-called' " Description
of the works " placed in
the entrance, states the start
date at September 2004. The
works were still
taking place in May
2006 - as can be seen in the
Photo gallery
('So-called' because when
compared with the evidence. See the compilation
in this
pack (2.4MB) highlighting
the on-going lies and deceit). (See also Mr Brian Gale )
Mr Gallagher knew that the works had
not been started . Indeed, he captured
this under point 29(6), 9
June 2004 , "(my) surveyor and (I) had
expressed concern that the major works (which
at that stage remained outstanding)."
The assessment by the Bar Council was:
"The Committee was satisfied that
Mr Gallagher's advice was realistic and
Ms McLean's attendance note of the conference
on 28 October 2003 shows that Mr
Gallagher carefully considered the options
open to you before recommending acceptance
of the offer"

|
This
assessment is hilarious when read
in the context of the subsequent
feeble and laughable 'get out clause'
from Mr Gallagher, 'dutifully' reported
by the Bar Council in its 3
June 2005 letter
"Mr Gallagher's
involvement concerned a time
frame of only about 3 weeks. "
...and also 'dutifully' captured
by the Legal
Services Ombudsman in
her 30
August 2005 reply to my
complaint against the Bar Council |
As Mr Gallagher had described my wanting to
be provided with the 2002 accounts as "a
counter offer" under point 19 of my 25
March 2005 reply I wrote
"I certainly would not describe my request
as a 'counter-offer' - as it relates to compliance
with the terms of my lease"
I also pointed out that
'I' raised the issue of breach of the terms
of my lease which, as the client, I certainly
should not have had to do.
The fact that no
reference is made to my lease in
Ms McLean's attendance
note is damning
evidence against Mr Gallagher (and PSB/W): they position
themselves as 'experts' in landlord-tenant
disputes in which the terms of leases play
the most critical part - and they ignore my
lease - in spite of my raising it at the meeting" (point
66, 25
March 2005 )
While under point 67 I highlighted:
"For
your information, CKFT and Mr Gallagher are
alone in their interpretation of the terms
of my lease. My position stems from the opinion
I obtained from several lawyers at: LEASE,
the Federation of Private Resident Associations,
and other lawyers I consulted - and is further
supported by the aforementioned"
I followed this by capturing - yet again - clauses
in my lease which clearly demonstrate that the
approach and method used by Steel Services-Martin
Russell Jones-Cawdery Kaye Fireman & Taylor breached my lease and added,
"You
have opted to ignore the fact that Mr Gallagher
dismissed my request for the 2002 accounts" (point
19, 25
March 2005 )
I highlighted that my not being provided with
the accounts amounted to a breach of my statutory
rights (point 20, 25
March 2005 )
I also drew attention to the fact that, having
finally managed to obtain a copy of the 2002
accounts in February 2005
"Not surprisingly,
they vindicate my conclusion that SS-MRJ had
something to hide in not providing me the 2002
accounts by the time of the 21 October 2003 offer. They
do not provide detail of "future costs, expenses
and outgoings" - Clause 2 (2) (e) and
Clause 2 (2) (f)." (point 21, 25
March 2005 ) (See also Pridie Brewster )
Under point 29 I wrote "In light of the
above - in relation to my request for a copy
of the 2002 accounts at the time of the 21
October 2003 offer - I again ask the question:
"Was
Mr Gallagher acting for me or the other side?" (point
136, 29
August 2004 )
I AM STILL ASKING THIS QUESTION
Considering the decision of the Bar
Council - and of the Legal Services Ombudsman - fair minded, reasonable visitor to the site,
do you see why I stated in the introduction
to the site that there is 'no avenue open to
me for justice and redress on this island'?
Back
to list
(3) I was in a "very weak position" as
I had "no technical defence to the claim" :
Mr Gallagher "did not view that there was
a technical defence of merit to the claim " (29(5), 9
June 2004)
Having "reconsidered this conclusion in
the light of the complaint" Mr Gallagher
stated he "stood by it" (29(5), 9
June 2004 )
Back
to list
(a) The LVT determination was a "mix
bag"
An 'alleged' accusation in my
complaint (point 2.2 in the summary) against
Mr Gallagher is that he (and Piper Smith Basham )
"In effect, opt(ed) to ignore the findings
contained in the 17 June 2003 report from the
LVT - (principally that some £200,000 (US$352,700) of
works are not specified/ lack specification)
as the only reference to this in the reply
reads: ".your client=s claim, as adjusted
to take account of the LVT=s determination
remains proceedings." - thereby, (as in the
case of the reference to my lease), making
it impossible to understand the issue
This is in spite of my surveyor having,
for the 28 October 2003 meeting: (i) documented
his assessment of Steel Services' revised costs
supplied with the offer; (ii) taken
Mr Gallagher through a detailed explanation
of his assessment, including referring extensively
to the LVT report in the process of explaining
his conclusions. (Mr Gallagher had been provided
with a copy of the LVT report ahead of the
meeting)"
Mr Gallagher replied
"There was no question