The year of:
The Leasehold
Valuation Tribunal hearings
and determination from which the impact
was a reduction of nearly 70% on the global
sum demanded - from £736,206
(US$1.3 million) to £236,000 (US$416,000)
Suffering extreme torment and anguish
from the actions by West
London County Court and Wandsworth
County Court, as well as injustice
'Suffering appalling treatment from Piper
Smith & Basham,
solicitors, as well as professional misconduct
by Mr Gallagher (' Allegedly ' as
my complaints have not been upheld by the Law
Society and the Bar Council - nor by the Legal
Services Ombudsman)
The 'offer' by Steel Services of £6,350
(US$11,200) + interest (!!) (the initial demand
was £14,400) (US$25,400)
The battles with the lawyers
Harassment and intimidation by
Kensington & Chelsea
police
The continuation of the bullying,
intimidation, harassment and blackmail
tactics by Mr Ladsky et. al. and their
aides
2 January 2003
On my return from holiday, I find an 'expert
witness' report, dated 13
December 2002 , written by Mr
Brian Gale, MRICS, Mr Andrew Ladsky's surveyor,
to the
LVT , in
which, in effect, he calls me a liar
as he claims on page 6 that I have been issued
with a detailed costing of the specification.
This report was delivered post the
17 December 2002 deadline, and therefore
in breach of the directions set
by the LVT. (See Brian
Gale and LVT sections)
I also find a letter dated 16
December 2002 from 'Ms Hathaway', MRICS,
, Martin
Russell Jones,. (Comparing this letter
with others sent by Mr Ladsky / 'Steel
Services' i.e. 25
January 2001 , 2
January 2002 and 14
November 2001 , I conclude that it
has most probably been written
by Mr Ladsky).
This letter is a work of fiction ,
riddled with lies and in which 'Ms Hathaway' in
effect calls me a liar.
3 January 2003 - 11h30

|
I can
sense that somebody is in the corridor
very close to the door to my flat.
When I open the door in order to
leave my flat, it is Mr Andrew Ladsky -
no doubt trying to listen in.
He immediately goes down the corridor
but, as this does not lead anywhere,
he turns back. He ends-up
walking barely a metre behind me
and, as he is doing this, says, I
am going to get you this year" with
a lot of venom in his voice. |
20 January 2003 - c. 12h40
As I had come up the stairs to go out of the
building, Mr Ladsky was about
to get into the lift. On seeing me, he says: "Better
luck next time!" followed
by a sarcastic laugh. I conclude he is
referring to the forthcoming 5th February 2003
LVT hearing where he is clearly counting on getting
the case closed.
c. 17 January 2003 - The tribunal's refusal
to my request for a postponement
One or two days earlier I had received a reply
from the LVT to my 12
January 2003 letter in which I requested
a postponement of the 5 February 2003 hearing.
I gave as reason the fact that I "still
have not been supplied with the priced specification
and cannot therefore instruct an expert witness
to determine the reasonableness of the cost
of specific remedies and thus determine specific
items of dispute for the trial" (i.e.
as per the directions set
by the LVT).
Please not that in my 18
December 2002 letter to the LVT, I had
already highlighted the breach of the tribunal's directions by
Martin
Russell Jones - and consequently my
inability to implement actions as per the instructions).
The LVT refused my
request . (See LVT section).

|
So, in
addition to West
London County Court ignoring, so far, two letters from
me ( 10
December 2002 and 17
December 2002 ), as well
as my defence ,
I have the tribunal which also
opts to ignore the contents of
my correspondence.
It leads me to the conclusion
that both the court and
the tribunal consider me as a non-entity and
that I might as well have been
writing in invisible ink. (See
below, 'end
January') |
In the case of the tribunal, I kick myself for
my naivety in believing in a claim made
by a government department; in this instance,
Mr John Prescott's
Office given that it
covers the LVTs.
Indeed, the LVTs are positioned as a forum for
resolving residential leasehold problems "without
the need for professional representation" .
That is proving to be definitely not
true. I am going to need 'professional
representation' - and fast!
It leads me into a frantic search. I do not
know where to turn to. I go back to the
LEASE site which lists pages of solicitors
claiming to be specialist in landlord-tenant
disputes. (Several months previously, I had visited
the site from which I identified two solicitors
I met with. One of them refused to give
me an idea of cost saying that this kind of dispute
is unpredictable. Equivalent to saying:
'write me a blank cheque').
I take a leap of faith and select a solicitor.
From a list of four names that he supplies me
with, I end-up selecting a surveyor. Hence, another
leap of faith.
Then starts the writing of correspondence to
brief the solicitor and surveyor on events to-date,
provide clarification, as well as copying of
documents. More evenings spent doing this - added
to all the other evenings, as well as weekends
that this nightmare has so far robbed me off.
23 January 2003
I receive a copy of a letter, dated 20
January 2003 written by Ms
Hathaway to
the LVT (following my request for postponement
of the 5th February hearing) in which
she, in effect, calls me a liar claiming
(like Mr
Brian Gale did in his 13
December 2002 report) that I have been
supplied with the priced specification.
(See below, 5 February 2003, for proof that
both lied)
End January 2003 - The 'get lost' from West
London County Court
In reply to my two letters (10 December 2002 and 17 December 2002 ) and my defence in
December in which I highlighted that the same
action had been referred to the LVT and consequently
requested that the action be stayed (suspended),
West London
County Court tells me in its 24
January 2003 letter that I should
ask CKFT whether
it agrees to this. Unbelievable! As
a litigant in person (i.e. not represented),
and considering events to date i.e. Mr Silverstone's 7
October 2002 and 21
October 2002 letters,
I conclude that there is no point my doing
this.
I also find it extraordinary that West London
County Court does not see that it has a role
to perform as a result of being informed of an
abuse of process of court - committed by an officer
of the court - which is what a solicitor is.
(NB: There most definitely is an abuse of process.
Not only have LEASE and another solicitor said
this to me, the following two letters
provide further proof of this: Ms McLean's letter
of 9
April 2003 to my then solicitor
and the 12
December 2002 letter
from one of the leaseholders' solicitors
to CKFT). Of course, as with every
other government departments I have been
in contact with: up to me to sort it
out!

|
Not
surprisingly, the LVT
refusal causes me enormous distress,
torment and anguish.
What is going to happen
next?
How am I going to deal
with it... on top of everything
else?
And more was about to be added
very shortly. |
30 January 2003 - Kensington & Chelsea
police officially records a complaint made
against me by Mr Andrew Ladsky
I receive a letter from Neil Watson
PC 206BS, Kensington & Chelsea
Police ,
dated 27
January 2003 , stating:

|
"The
police have been informed by a
Mr Andrew Ladsky that you verbally
abused him in public over some
sort of dispute revolving around
your premises. Indeed, his
version of events have been confirmed
by a witness....
Of perhaps greater
importance is the fact that any
further such outbursts may result
in charges of harassment
being made against you, as this
initial complaint has been fully
recorded by the police. I
wish to make it clear that my role
in this is purely neutral at the
moment....".
( NB: Timing
is just before the LVT hearing
of 5th February 2003) |

|
I laugh
on receiving this letter as I visualise
the scene: a man, standing in a police
station, saying,
"Mr Policeman, a woman swore
at me"
(Or was it just a phone call to
Kensington and Chelsea police?)
I am most definitely not going
to phone him. The 2002
events (Feb-March and May-July)
are still very fresh in my mind.
I opt to ignore it and to wait
and see what the next instalment
brings. |
5 February 2003 - Letter from Mr Lanny Silverstone

|
Letter
from Mr Lanny Silverstone ,
CKFT, dated 4
February 2003 , to me stating " .has
come to [their] attention
from Mr Ladsky, tenant
( !!!) of
flat 35. you shouted abusive
and foul-mouthed remarks at him . in
front of a guest.
We further
understand not first incident
of this description. incidents
have been reported to police...
Mr Ladsky or the police may take
action against you ...
your behaviour
constitutes breach of covenant...
any repetition or further complaint
our client will take injunctive
steps prior to other
proceedings being formalised
to restrain you.
To date you
have made quite improper
and defamatory allegations regarding
the probity of our client
company and also of Mr Ladsky..". |
(NB: Ditto in terms of timing: calculated to
arrive on the day of the LVT hearing). (Well,
Mr Ladsky did say to me on 3 January 2003 "I
am going to get you this year!" )
5 February 2003 - The tribunal hearing
Before the start of the LVT hearing, my Counsel
'grills' me on previous events with the
LVT, showing some irritation. I break down
in tears. The stress of the last 12 months
is taking its toll. The last thing I need
is my Counsel also 'getting at me'. However,
on the upside, we determine that, in sending
me a copy of Steel Services 7
August 2002 application, the LVT had NOT
included any of the supporting enclosures.
My brother arrives to give me moral support.
(Not a blood brother, but a brother in
every other way)
When we arrive in the main reception area upstairs,
Ms Hathaway, MRICS, Martin
Russell Jones is there. My Counsel introduces
himself. Then my surveyor and solicitor
arrive. This is followed by the arrival
of Mr Andrew Ladsky who looks at my party
and goes to talk to Ms Hathaway. Until
the start of the hearing, Mr Ladsky spends
the time on his mobile phone. He looks
very animated. (Internally, I have a
good laugh. About time!)
Very clearly, he had not expected me to turn
up with professional advisers. In fact, considering
the atmosphere and eye contacts at the beginning
of the hearing, nor have the members of the panel.
(Until then, there had not been communication
on my behalf from a professional adviser). The
beginning of the hearing is decidedly 'frosty' - leading
my Counsel to make a remark to the Chair.

|
At the
hearing, Mr Ladsky (who
was a member of Steel Services party
throughout the hearings) says to
the Chair,
" Will Ms Rawé pay
the £250,000 (US$441,000) of
additional costs that
will be incurred as a result
of the delay in the start of
the works due to hearing?"
The Chair replies that I am perfectly
within my rights to challenge the
application made by Steel Services. |
This is captured in the 17 June 2003 LVT/SC/007/120/02 report (ref. #992 on the LVT database) under
point 64 "Although she is in the minority, the
Respondent's legal right to challenge
the Applicant's proposal, as she has done,
cannot be fettered"
( NB : Both, Cawdery Kaye Fireman & Taylor and Martin
Russell Jones, subsequently accused me
of being responsible for the LVT action. Please
note that it is Steel Services - not I - who
filed the 7
August 2002 application to the LVT.
For
example, in the case of CKFT, Mr Silverstone 25
June 2003 letter to me ".without
going through the costly LVT process which
has now resulted in a percentage uplift in
the contract figure and a significant delay
in the project" .
Ms Ayesha Salim, CKFT, 21
October 2003 'offer' "Your client's
decision to challenge both the LVT decision
and to continue to defend these proceedings
is her own. Her decision to do so has caused
inconvenience and expense to all the lessees
of the building"
Please note that it is Steel Services that kept
challenging the LVT determination, not I - as
evidenced by the statement in the 21
October 2003 'offer' "our client has once
again (NB: !!!) reviewed
the revised apportionment dated 24 June 2003" .
Note also that if Steel Services was unhappy
with the LVT determination, the proper channel
to follow was to refer it to the Lands Tribunal.
In relation to Martin
Russell Jones, see Mr
Barrie Martin's false accusations in his 4
August 2004 letter to me - and
my reply of 11
August 2004 )
As to Ms Hathaway's previous claims (e.g. her 20
January 2003 letter to the LVT) that I
had been supplied with a copy of the priced
specification, initially, she vehemently asserts
this claim yet again during the hearing, by
saying: "the porter has confirmed that
Ms Rawé has looked at them" . She
then contradicts herself in reply to a question
from my Counsel, by saying: "Oh!,
there are so many reports in the porter's lodge,
he would not know which is which!"

|
This
is captured under point 14 of the 17
June 2003 LVT report
"Ms
Hathaway (of Martin Russell Jones),
on behalf of the Applicant, resisted
the application for an adjournment.
She maintained that Ms Dit-Rawé had
seen the specification... but
was unsure as to whether this
had been a priced version"
The same damning evidence is found
in Mr
Brian Gale's 24 February 2003 report,
under point 2.04: "the
un-priced or priced Specification...has
been. freely available for all
lessees to view" ). |
See also LVT , Brian
Gale and Martin
Russell Jones for further evidence, namely letters from
other leaseholders to Mr Hathaway and the LVT)
When my counsel raised the issue of the missing
enclosures during the hearing, the Chair
turned to the clerk asking him to confirm
this - to which he replied: "Not
all the residents were copied on the enclosures"
The outcome was that, while the LVT had denied
my 12
January 2003 request for an adjournment
of the hearing, it was finally granted at the
5 February hearing - as captured under point
16 of the 17
June 2003 LVT report: "In the interest
of justice, the Tribunal agreed to an adjournment."

|
"In
the interest of justice" (!!!).
Why had there not been 'justice'
before?
I attribute this change of position
by the LVT to the fact that I was
represented.
Why was it necessary for
me to spend a very significant
part of my life-savings to employ
a barrister (and concurrent solicitor)
to repeat what I had already
said to the LVT on numerous occasions
previously? (See
LVT section for more detail) |
11 February 2003
I receive another letter from Neil Watson
PC 206BS Kensington & Chelsea
Police ,
dated 6
February 2003 - again asking me to contact
him.

|
As the
only communication I am prepared
to have with Kensington & Chelsea
police is in writing, I write a reply,
dated 11
February 2003 , in which I
ask for very precise details - in
writing - of the accusation and
send the letter recorded delivery.
There has been no 'official'
follow-up whatsoever by the police
since. (See Police section for further detail) |
(NOTE : As detailed
previously, in 2002 (in relation to the
handling of my complaint by Kensington & Chelsea
police), I eventually escalated my complaint
to the Chair of the
Metropolitan Police Authority, asking for
his assistance in my letter dated 5
May 2002 .
After some chasing, I received a reply, dated 11
July 2002 , in which he wrote, among others "...the
police must act only on the basis of
established facts" .
Compare this with the 27
January 2003 letter from Neil Watson PC
206BS following Mr Ladsky reporting me for "swearing
at him"
" Of
perhaps greater importance is the fact that
any further such outbursts may result in charges
of harassment being made against you, as this
initial complaint has been fully recorded by
the police."
Very clearly, no concern here about: "acting
only on the basis of established facts"
And, obviously, another of the Chair's comment
in his 11
July 2002 letter that I must ".appreciate
that officers have to act with consideration
for resource and time expenditure when
investigating a case such as this" did
not apply in this instance either.
I concluded my 4
August 2002 reply to the Chair by
stating: ".my dealings with the police
in recent months, have led me to totally - and
for ever - lose my confidence in the British
police" . The above events in 2003
only served to reinforce my feelings. (And
have led me to my current thinking that,
if I am attacked, there is no point my
contacting Kensington & Chelsea police)
(The 7
August 2002 reply from the Chair's
Office to my 4 August 2002 letter, once
again stresses the need for evidence
for the police to act)
Additional food for thought: it seems that if
Mr Ladsky was 11 years old, I and the other
residents would have been able to get an ASBO (Anti-social
behaviour order) placed on him. The attached Daily
Mail article of 6
June 2005 reported such a case "The...
order...prohibits (the
child)...from harassment that would
cause alarm." .

|
Why
is it that landlords and their
aides are free to terrorise leaseholders?
(The Evening
Standard article
of 3 December 2003 , headed "Left
homeless for £25" (US$44)
indicates that a leaseholder
had a similar experience:
"neither
the police nor Hastings borough
council will act" ) |
13 March 2003
First day of the substantive hearing at the
LVT. I feel very nervous and stressed, partly
because of all the recent events, and partly
because I have at the back of my mind Mr Ladsky's
question to the Chair on 5 February "Will
Ms Rawé pay the £250,000 (US$441,000) of
additional costs that will be incurred as a result
of the delay in the start of the works due to
hearing?" .
I also remember one leaseholder who wrote me
in her 1
November 2002 letter
".Mr Ladsky acted like a petty tyrant,
and I am not afraid to put on record
that I believe that he is capable of any unscrupulous
actions in order to achieve his aims" .
I also know what he and 'Steel Services' i.e.
him, did to the Head
of the Residents Association, the Elderly
Resident, Other
Residents and Nucleus .
At the hearing, the opening statement from Mr
Warwick, Steel Services' Counsel ,
is that "the reason [I have] been
challenging the service charge demand is because
I did not want to pay it" . (Although
it very clearly was not his meaning), damn
right I am not going to pay £14,400 (US$25,400)
without justification.

|
Prior
to the hearing, I had received a
copy of Mr
Brian Gale 24 February
2003 " Expert
Report /Proof of Evidence " to
the LVT. Sections 2 and
5 of this report can only be described
as 'a pack of lies' .
My 13
March 2003 reply to Mr Brian
Gale's section 2 and 5 was handed
by my Counsel to the LVT Panel
and Steel Services party on 28
April 2003 (third and final day
of the LVT substantive hearings).
(See Brian
Gale for further detail) |
And Mr Gale certainly proved to be a
liar .
In his 13
December 2002 "Expert Witness" report to the LVT, Mr Gale
wrote under Section 4 -1.4
"I am able to categorically state
that the Specification makes NO provisions
for any construction of an additional floor
nor any future requirement in the building
to create a penthouse flat"
In fact, when the works started in September
2004, so did the construction of the penthouse
flat.

Jefferson House
July 2002 |
|

Jefferson House
September 2005 |
Evidently, such as the 'incidental' cost of
building a penthouse flat and significant
works to the flat below. Of course, as
Mr Gale wrote
in his February 2002 report
"...the roof had
exceeded [its] modern life span" and
there was ".water ingress" to "some
of the properties" , "replacing
the asphalt roof" "needed to be
dealt with as a matter of urgency" .
It was
so urgent, that the works were started
2.5 years later in September 2004. See Brian
Gale section for further detail.
As can be seen in his letter of 19
October 2005 , Mr Gale continued
to misrepresent the works undertaken to the
very end:
"...Mansells, the contractors undertaking
the works.have now completed the external redecoration" .
"The external redecoration" ?
How about the construction of the
penthouse flat?
How about the conversion of flats
resulting in the addition of three other flats?
These works resulted in 39
flats v. 35 flats
at the start of the works. (For evidence
of 35 flats at the start of the works see,
for example, point 7 of the 17
June 2003 LVT report).
Mr Brian Gale proved to be a liar, like
Ms Hathaway:
Her letter to me of 26
March 2002 : "Your suggestion
that the appointment of professional advisors
is in any way connected with any planning application
is incorrect"
Her 30
August 2002 letter to me: "We
are informed that there is no intention to
build the penthouse at the current time"
Her 4
March 2003 letter to Brian Gale (which
was supplied as part of
the evidence during
the tribunal hearings in March-April 2003):
"...regarding the proposed penthouse...although
the planning permission was granted
it was subsequently
found that the scheme was not a viable
proposition...there are no plans to
build the penthouse at the property"
And their 'dear' client, Mr Andrew Ladsky:
In his letter to me (and other
leaseholders) dated 25
January 2001 : ".the costs of any additional
floor on the property will NOT be borne by
the residents. All tenants are of course protected
by the Landlord and Tenant Acts to ensure those
carrying out any works do so reasonably."
As to how the contractors, Mansell
Construction Services and /
or Mr
Brian Gale, describe what they did
to the roof (from the " description
of the works " , headed with: Principal
Contract: Mansells Construction)
"General repair and refurbishment of the
main structure of Jefferson House, 11 Basil
St, to include cutting out of spalled and defective
brickwork and replacing to match, replacing
asphalt roofs , redecoration externally,
redecoration of internal common areas, replacement
of lift"
Very clearly, Mansell - Mr Gale have a very
unique interpretation of "replacing asphalt
roof" ! Maybe it's a question
of economy with words as they headed this "Brief
description of work".
18 March 2003
For the second time now, I set-up another 'Keep
safe' facility with the post office because my
regular postman is going on holiday.
24 March 2003
I receive a notice of a Charging Order hearing,
dated 21
March 2003 , stating that it is due to
take place on 4 April 2003 (This
amounted to giving me a 7 working day
notice. Typical
of West
London County Court that has consistently
demonstrated the most amazing haste in
responding to Steel Services i.e. Mr Ladsky
et. al's / CKFT's requests for hearings).
I am in a state of shock and panic, as I have
absolutely no idea what a Charging Order hearing
is. It leads me into a frantic search which includes
phoning the Department for Constitutional Affairs
i.e. Lord Falconer
of Thoroton 's department.
The person I speak to says that she does not
know the answer. (But she offers to send me a
complaint form (!!!))
25 and 30 March 2003

|
I reply
to the court on 25
March 2003 highlighting the
fact that the LVT had specifically
told leaseholders to not pay the
service charge demanded until it
had reached a decision - and it
had therefore been implemented
(we were given a leaflet to
emphasise the point - see page
5)
In spite of this letter, West
London County Court still
persists in telling me, in its 27
March 2003 letter, that
the 4 April 2003 Charging Order
concerns me "Please note
that your request will be considered
at the hearing on 4th April
2003" |
I leave messages with the solicitor acting for
me at the time, and send a fax. He does not return
my calls. The next day I receive a letter from
him telling me that he is advising me in relation
to the LVT - not the court action. Hence, I need
to pay £2,000 (US$3,500) in
advance to receive advice. In other
words, at the time, in order to get a reply to
what is a straightforward question for a solicitor.
(By then, I had already paid c. £9,000
(US$15,900) in fees)
30 March 2003

|
At my
wits end, on 30
March 2003 , I send a letter
to the members of the LVT Panel
- on which I copy the District
Judge stating, among others:
"...I requested (once again)
that the action be stayed explaining,
among others, that: 1. at the
LVT pre-trial hearing on 29 October
2002 Mr J.C. Sharma JP FRICS
had in effect told the residents
to not pay the service charge
demanded for the major works
until the LVT had reached a decision.
How can it be that two government
departments - who have been made
aware of a conflict as a result
of actions they are concurrently
undertaking - have no line of
communication?" |
1 April 2003
Minutes away from giving an extra £2,000
(US$3,500) to my solicitor because I cannot determine
what a Charging Order is, through my network
of contacts, I am told that a Charging Order
implies that a judgement has been entered against
me. Has a judgement been entered against me? I
reply that I have not received any communication
to this effect.
Armed with this information - in particular
the 'correct' terminology - I phone West
London County court, now for the third time.
Having said (at a very slow pace) "there
cannot be a charging order against me because
there has not been a judgement against
me" ,
at this point I am put through to somebody
else who, I believe, is the court manager.
Following my repeating the same thing (again
very slowly), I get the reply: "No,
the charging order is not against you, it's against
other residents" .

|
I went
through days of hell, and nearly
spent another £2,000 (US$3,500)
of my life-savings, to finally be
told that the action has nothing
to do with me!
And do I get an apology from the
court? Of course
not! (And not
even following my 29
June 2004 'cry for help'
to Lord Falconer. See Lord
Falconer of Thoroton for my comments to
the 23
August 2004 reply from
the Court Service |
My follow-up to the court on this is captured
in my 1
April 2003 letter. You will see my statement
that I attribute events to among, others, mismanagement.
Although denied by Lord Thoroton when challenged
on this by the media, there appears to
be a widely held perception of gross incompetence
and mismanagement of the courts. Indeed,
even a judge was reported in 2001 as holding
this view ( District
Judge used the term "gross incompetence" in
relation to administrative staff in a
Magistrates Court )
And more was yet to come from the courts. on
four other occasions. (See 16 June 2003, 31
March 2004, 28
May 2004 and 12
June 2004)
4 April 2003 - A wasted journey to West London County that cost me over £700 (US$1,300)
During my conversation with the court manager
on 1 st April, he tells me that although
the hearing does not concern me, there may nonetheless
be benefit in my attending. Not knowing
what to expect, I ask my surveyor to accompany
me. When
we arrive at the court, we are informed
that the hearing had been cancelled. A consent
order relating to the 7th Defendant, dated 2
April 2003 , had been faxed to the court
by CKFT.
Of particular importance: the document states "Judgment against the Seventh Defendant dated 28 January 2003...." THIS IS ABSOLUTELY UNBELIEVABLE! SUCH INJUSTICE!
In addition to my surveyor's fees of £600 (US$1,000) , it
also cost me half a day of my annual leave. Added
to the other days of my annual leave I had so
far been using up - and would need to use (e.g.
LVT hearings), I am not going to have much holiday
left for the year.
As I am returning to work from West London County
Court , when I arrive on the corner of
[ ] and [ ], I notice a man standing
on the corner of [ ] and [ ]. He is looking
at me. Aged in his 30's, he looks like
a bouncer. Short dark hair, heavy features .
He is wearing a suit.
I turn left into [ ] and cross to the other
side of the street in the direction of
[ ]. Before
going into [ ], I turn round. The man
is still looking at me. I purposely hold
his gaze. He turns away and walks in the
direction of [ ]. I stay where I am and
keep looking at him. When he is at the
height of the post office, on the corner with
[ ], he turns round and looks in my direction.
I stand there, looking back at him. We stay like
that for c. 1 minute, at which point I go into
[ ].
Easter break 2003
There is no heating and no hot water
for 5 days from Good Friday 18 April
2003 until Wednesday 23 April 2003. Mr
Ladsky is away during that weekend.

|
There
is nothing the residents can do :
the porter cannot be reached (the
'emergency number' diverts to an
answer machine in his cubby-hole);
there is no emergency number for
Martin
Russell Jones;
it is impossible to access the
boiler - even if residents knew
where it is - it is likely to be
locked.
While this event may be a coincidence,
I very much doubt it. |
May 2003
The difficulty of keeping track of when my regular
postman will be away, added to the unreliability
of the 'Keep safe' service, leads me to set-up
a PO Box.
Doing this requires my needing to go to the
sorting office some way down the Kings Road to
get my mail. This is very inconvenient, but my
only option for ensuring that I get my mail.
Note at 2005 and 2006: At least, that is what
I was expecting. In reality, the service has
proved to be particularly unreliable leading
me to file several
complaints, eventually to
the CEO - to whom I yet again in March 2006.
(Another example of being 'trapped' as there
is no alternative. At least, I now have a 'direct
line to the top' to which I report my complaints.
Lucky me!)
End of May 2003

|
I receive
a 23
May 2003 application for a
Case Management Conference to West
London County Court written by
Mr Silverstone, CKFT, stating:
"As you are aware we are solicitors
for the Claimant. The
Claimant has obtained judgment or
settled proceedings against all
Defendants, except the following". The
list states the 1st , 2nd ,
5th and 7th Defendant.
But the LVT has NOT issued
its determination. (It dated its
report 17
June 2003 and I only received
it on 22 June 2003) (see this
date for further detail) |
As there were 11 leaseholders listed on the 29
November 2002 claim, it provides incontrovertible
evidence ( "has obtained judgement" )
that West
London County Court was instrumental
in making seven leaseholders
pay before the LVT issued
its determination.
Hence, West London County
Court totally ignored the fact that
leaseholders had very specifically been told
by the Tribunal to not
pay - until it had issued its determination - and
it had been implemented .
For further evidence that it did this, see earlier
on my 25
March 2003 letter to the court in
which I had - yet again - brought attention
to the ongoing LVT action, as well as
reporting - very clearly - that we, the leaseholders,
had specifically been told by the LVT
to not pay the service charge.
See also earlier on: (1) its 27
March 2003 reply, insisting that the action
concerned me; (2) my 30
March 2003 letter to the LVT Panel -
on which I copied the District Judge - and
in which I again repeated what we had been
told by the LVT; (3) my being finally told,
as a result of phoning the court on 1 April
2003 saying
"there cannot be a Charging Order against
me because there has not been a judgement against
me"
At this point I was told "No, the
Charging Order is not against you, it is
against other residents" (as
captured in my 1
April 2003 letter to the court). (The
fact that a Charging Order can only be
issued once a judgement has been entered
was also confirmed by the Court
Service in its 23
August 2004 reply)
(NB: Remember also that between December 2002
and March 2003 I wrote four letters to
West London
County Court highlighting the
LVT proceedings and consequently requested
that the action be stayed. I had also referred
to the LVT proceedings in my
defence to the claim dated 17 December
2002 .
As just explained, in two of my letters, 25
March 2003 and 30
March 2003, I had made specific reference
to the fact that the LVT had specifically
told leaseholders to not
pay the service charge demanded)

|
This
is so, so MORALLY WRONG. SUCH INJUSTICE.
Indeed, (jumping the gun here
a bit), consider the above events
in the context of point 64, on
page 15 of the 17
June 2003 LVT report:
"...the Respondent
and other tenants (NB
!!!) could
not be forced to contribute
in the case of improvements
and/or works not determined
as reasonable by the Tribunal..." (See
below, 22 June 2003, for further
detail) |
During the 24
June 2003 hearing, the judge told Mr Lanny
Silverstone, CKFT, that he was "wasting
my time and the court's time. The LVT report
has just been issued. You need to give the
Defendants time to review it" (leading
the judge to award
costs to me (and the other leaseholders
present))
Consider the latter part of the judge's comment
in light of the above.
Consider also the LVT's 21
July 2003 reply to Mr Silverstone's letter
of 17
July 2003
"It is not the duty of the Tribunal to
assess the particular contribution payable
by any specific tenant but only to
determine the reasonableness , or
otherwise of the service charges as
a whole to go on the service charge account from
which no doubt you can assess the proportion
for that particular tenant "
Fair minded, reasonable visitor
to the site: can you see why in the introduction
to the site, I stated that there is 'no avenue
open to me for justice and redress'?
16 June 2003

|
I receive a Notice
of Hearing from West
London County Court dated 12
June 2003 . It states that
the hearing is due to take place
on 24 June 2003. (Again, barely
one week notice)
I have not received a copy of
the LVT determination (as it signed
it on 17
June 2003 ). I consequently
see myself as, yet again, being
hounded by the court.
In fact, I feel that 'persecuted'
is by now a more appropriate description. |
17 June 2003
In my 17
June 2003 letter to the District
Judge, West
London County Court, I
state, among others,

|
"Why
are you asking me to attend a hearing?
Why aren't you instead asking
me whether the LVT has reached
a decision?
Better still, why
are you not communicating with
the LVT?
For the second time now your
court is causing me untold torment,
anguish and distress.
Why is your court putting
me in this situation of needing
to get very costly legal advice
when in fact I have yet to hear
from the LVT?
Why is it that your
court is not waiting for this
decision? Until there
is a decision from the LVT, what
can you enforce?
But maybe I am going
through this hell for nothing. Maybe
this is a repeat of what happened
in March. i.e. has nothing
to do with me. Is that the
case?" |
22 June 2003
I receive the 17 June 2003 LVT/SC/007/120/02 LVT determination (ref. #992 on the LVT database).
It is a damning report (which endorses my surveyor's
assessment of 24
February 2003 ) but it does not include
a summary of the impact of the determination
on the global sum demanded.
Hence, the LVT failed to perform its
remit. (Evidence that this was its
remit, is captured under point 1 of its 17
June 2003 report and was also confirmed,
for example by the LVT Clerk on his voicemail
message to Piper Smith Basham ".the tribunal
is looking to determine the reasonableness
of the global figure that's attributable
to the whole block" - as captured in
Ms McLean's 9
April 2002 letter. It is also evidenced
by the LVT's 17
July 2003 reply to Mr Silverstone)
(See LVT for my follow-up actions - IN VAIN
with the Head of the LVTs: she twice refused
my request to have a summary included. See also Mr John Prescott # 1.3 , # 1.4 )
(As an introduction to the next few paragraphs,
please note that my surveyor, Mr Brock, LSM Partners,
is a Chartered Surveyor, member of the RICS.
To which I will add: a highly professional surveyor,
with the utmost level of integrity)
Based on my surveyor's
assessment (as the LVT, 'conveniently'
for Steel Services, failed to provide a 'global'
assessment), the outcome of the LVT determination,
in relation to the original global sum
demanded of £736,206
(US$1.3 million) (£564,467 excl. VAT
and 11% management fees) is:
Amount disallowed by the LVT because
improvements: £169,498 (US$299,000) (£129,958
excl. VAT and fees) = 23% of
the global sum demanded (point 48, 29
August 2004)
Amount for which the LVT could
not make a determination due to lack of
specification = £188,784 (US$333,000) (£144,745
excl. VAT and fees) = 25.6% of
the global sum demanded (point 48, 29
August 2004)
A view supported by the LVT (*) ,
considering the terms of the lease,
as well as Royal Institute of Chartered Surveyors
best practice, that the reserve fund should
be used as contribution: £141,977
(US$250,000) - or 19.3% of
the global sum demanded (point 48, 29
August 2004 )
Leaving an amount that can be charged of £235,947
(US$416,000) - or 32% of the original
sum demanded.
In other words, £500,000
(US$882,000) of
the sum demanded was NOT considered
as reasonable .
My share of this at 1.956% equals £4,615 (US$8,140)
(vs. the £14,400 (US$25,400)
originally demanded and for which a claim had
been filed against me on 29
November 2002 by Ms Hathaway - under a Statement
of Truth (1.1MB))
Hence, it provides overwhelming evidence
that the original demand was extortionate.
A scam!
Without a summary, I foresee that that the battle
with Mr Ladsky et. al. is going to continue.
(I subsequently asked the Head
LVT, to include a summary - as evidenced
by my letters of 6
September 2003 and 6
October 2003 . Her initial refusal was
in her 12
September 2003 letter, the second
in her 26
November 2003 reply.
In between, I received a 6
October 2003 letter from Mr
Prescott's Office (on which I had copied my 6
September 2003 letter) stating ".unfortunately,
the Leasehold Valuation Tribunal is unable
to re-open your case"
(*) In the £500,000
(US$882,000) I have included £141,000 (US$249,000)
of contingency fund. My Counsel raised
it as an issue during the hearing as Steel Services
/ Martin
Russell Jones had not used it
as contribution towards the costs - and were
refusing to do so, in spite of, among others,
having stated this in the 7
June 2001 letter. (This is captured under
point 34 of the LVT determination). (But
it subsequently did in my case - see the 21
October 2003 'offer'. I believe this
to be because, among others, I had
the 7 June 2001 letter from Ms Hathaway)
Although the LVT said to not have the jurisdiction
to force Steel Services to use the contingency
fund, considering Clause 2(2)(e) of the lease (captured
under point 59 of the LVT report), under
points 62 the LVT quotes from the RICS
Code. (As you can see at the beginning
of My Diary - Year
2004, as well as under
the RICS section this 'so
called' code is a complete and utter joke)
22 June 2003
As I have now received the LVT determination,
on 22
June 2003 , I write another letter to the District
Judge in which I highlight, among
others, that, "The judgement remains open
to appeal to the Lands Tribunal."
Well, in spite of this, the judge decides to
nonetheless hold the hearing on 24 June 2003.
24 June 2003
A combination of costs and time factor (due
to West London
County Court's 'jumping' at CKFT's
requests, as well as crass incompetence) lead
me to represent myself at the hearing .
It is a scary, intimidating experience.
I have never set foot in a court in my life.

|
In addition, Mr
Lanny Silverstone , CKFT , hands me in the court's waiting
area, 10 minutes before
seeing the judge , a Draft
order and Case summary , neither
of which I have seen before .
I tell him that there is absolutely
no way I am going to comment on
these given the situation in which
the documents are given to me.
He mumbles something in agreement
but, clearly intends to produce
them during the hearing. |
With these documents, Mr Silverstone also hands
me a schedule of " Major
works apportionment, revised" on Martin
Russell Jones headed paper. Relative to the
amount on the claim, the sum demanded of me
(and five other leaseholders) has been reduced
by 24.19%. Mr Silverstone does not supply me
with any documentation, or indeed explanation,
as to how this reduction has been achieved.
While we are waiting to see the judge, I also
say to Mr Silverstone that I find it absolutely
outrageous that the court has been instrumental
in making seven leaseholders pay before the
LVT had issued its determination (see CKFT 23
May 2003 letter to the court). He replies, "they
made a commercial decision" . Yes,
the Business
model had worked - yet again!)
The judge starts by saying
that the court has received a useful letter from
me. At this point, I give a copy of my 22
June 2003 letter to the court to all those
present. She turns to Mr Silverstone and asks
him why he has asked for a hearing. Put on
the spot, he looks very ill at ease, like a
school boy being told off.
She continues, "you must give the residents
time to look at the LVT determination" .
(NB: How about the other leaseholders
who were made to pay BEFORE the
LVT issued its report? (as discussed
under 'end
May 2003')
THIS IS VERY WRONG.
While I ended-up being the only leaseholder
challenging the application (and none of
the other leaseholders have contributed to my £32,000
(US$56,500) LVT costs), it does not alter
the fact that the determination applies
to the WHOLE block.
Indeed, this is captured under point 64 of the 17 June 2003 LVT/SC/007/120/02 determination (ref. #992 on the LVT database) under point 64: ". the
Respondent and other tenants (NB
!!!) could not be forced to
contribute in the case of improvements and
/ or works not determined as reasonable by
the Tribunal")
See West
London County Court # 7 and # 8 for detail)

|
The judge
reprimands Mr Silverstone by saying "You
are wasting my time and the court's
time" .
Great, how about my time?
And why is it that no notice was
taken of my request to cancel the
hearing?
Oh! but of course: who
am I relative to a solicitor? |
She orders that Steel Services pays my costs
for the day (and that of other leaseholders present) - and
obviously, refuses Mr Silverstone's demand that
I (and the other leaseholders) pay his client's
costs for the day. (This was captured in an Order
dated 24
June 2003 )
Given these events, I hold the view that the
hearing should not have taken place. What
Steel Services-CKFT wanted out of the day was
the opportunity to put more pressure on me (and
the other leaseholders) to pay what it demanded
- and the judge obliged (wasting
taxpayers' money in the process).
(If you consider the cost of all the court and
tribunal hearings connected with landlord-tenant
disputes, the leasehold system is costing
everybody in the UK a lot of money .
(Consider that Steel Services only paid £500
(US$880) to file the 29 November 2002
claim against
11 leaseholders). Money that could be
spent on hospitals, increasing 'senior
citizens' pensions, caring for children with
disabilities, providing homes to the homeless,
facilities for the visually impaired, etc,
etc.
It is
sickening. All to help a minority line
their pockets at the expense of the majority)
15 July 2003
I send a letter to the judge at West London
County Court, dated 15
July 2003 , highlighting the
findings from the LVT determination and that
Steel Services-Martin Russell Jones have
not implemented them.
Sunday 27 July 2003 - Around 13h00

|
My kitchen
window is open indicating that I
am in the flat.
Mr Ladsky holds
a conversation with some people
for c. 15 minutes while leaning
against the railing immediately
in front of my window.
I view this as harassment and
attempt to intimidate. |
(NB: I reported this (and the 27 August 2003
event) in my 28
August 2003 letter to Ms Lisa
McLean , Piper
Smith Basham , by then,
my newly appointed solicitors. In her 1
September 2003 letter she wrote that
she had "noted my comments about Mr Ladsky" .
While in her 4
September 2003 letter she wrote "The
references to Mr Ladsky are, I feel, a separate
issue. If his actions (and of course it would
have to be proved that they were his or his
agents actions) amount to harassment and intimidation
then you could consider injunctive proceedings.
These would be entirely separate and as you
can imagine not inexpensive. The matters you
refer to are not sufficient (unfortunately)
to justify an injunction being brought" .
While Ms McLean did not ask me whether other
incidents had occurred, on 19
August 2003 I had supplied her with, among
others, a copy of the 4
February 2003 letter to me from Mr Lanny
Silverstone, CKFT, containing false accusations,
as well as the fact that Mr Ladsky had reported
me to Kensington & Chelsea police.
It is worth noting that I encountered
the same kind of attitude from Mr Gallagher,
counsel, when I reported, at the 28
October 2003 meeting with him, that
I had suffered on-going harassment and intimidation,
as well as assault from the time I challenged
the true nature of the works.
Commenting on this under point 29(14) of his 9
June 2004 reply to my complaint, Mr Gallagher
wrote
"Though I was virtually certain
that NKDR did not have a viable
claim against the landlord"
This comment (among others) led me to write
a 7-page reply in my 29
August 2004 response (under points 106 - 117)
highlighting all the instances of harassment
and intimidation I and other residents, as
well as our local Citizen Advice Bureau had
suffered.
Evidently not expecting that I had this
comprehensive amount of evidence against Mr
Ladsky , in his 11
October 2004 reply, under point 4(7)
Mr Gallagher wrote "the allegations of
harassment by Mr Ladsky and Mr Ladsky's complaint
to the police etc - these are not matters
that appear to relate to the allegations
against me and were not matters discussed
in conference, save for a very summary overview"
Funny how Mr Gallagher initially had an opinion
that I " did not have a viable claim against
the landlord" and then changed tack claiming
that it was only briefly discussed. As I wrote
under point 22 of my 31
October 2004 reply, "Mr Gallagher
is underplaying my reply to his point 29 (14)"
9 August 2003
I write another letter to the judge in
West London
County Court, dated 9
August 2003 stating, among others
"There are no side deals to be
made with the Claimant . costs
must be totally clear and transparent - to
ALL lessees . What each lessee is
required to pay is clearly defined by means
of a fixed percentage (see the attached list
of percentage for each of the 35 flats supplied
by SSL-Martin Russell Jones in their 7
August 2002 application to the LVT"
Nowhere does the lease state that the share
of the service charges payable by individual
lessees is dependent on:
(1)Their amount of 'backbone' and courage
to challenge a demand for money they do not
owe
(2) Their resistance to prolonged harassment
and intimidation
(3) Their determination to persist in the
face of adversity and their ability to handle
the resulting torment, anguish and distress"
In between CKFT's application for a hearing
on 26 August 2003 and the 24 June 2003 hearing,
it had sent me three letters ( 25
June 2003 , 24
July 2003 and 7
August 2003 ) in which it used what
can only be described as bullying, blackmail
and intimidation tactics in an attempt
to force me to strike a deal. (No, I am
not going to write 'allegedly'. I believe
the evidence speaks for itself)

|
As can
be seen under Mr
Gallagher , he held
the view that the fact I did not
want to 'strike a deal' with Steel
Services was one of the factors that
worked against me
"consider the fact
that NKDR had not accepted previous
invitations to attend discussions
on settlement in the light of
the LVT determination" (point
66, 9
June 2004 ); [I] "expressly
rejected CKFT's offers of a
round table." (point 15, 9
June 2004 )
In other words, Mr Gallagher
held against me the fact I have
strong moral principles that
prevented me from being treated
differently from the other leaseholders
i.e. striking a deal on terms
other than those specified in
my lease. |
As you would expect, my
lease (Clause 2(2)(c)(i) of) makes it
abundantly clear that there is a set and equitable
manner for the allocation of the service charges
among the leaseholders. (Other evidence includes:
(1) Ms Hathaway's 30
August 2002 letter to me "The amount
demanded is as the terms of the lease.
There is no separate list. Details of the percentages
are included in the schedules to previous
accounts. The
sum demanded is based on the percentage
of your lease, which is 1.956%..."
(2) These percentages were
supplied by Steel Services-Martin
Russell Jones with the 7
August 2002 application to the LVT. They
are also clearly evidenced, among others by
the documents supplied to the court by CKFT,
for the 24
June 2003 hearing and the 26
August 2003 hearing.
(3) The LVT's 21
July 2003 reply to Mr Silverstone, CKFT,
letter of 17
July 2003 ".duty of the Tribunal..
to determine the reasonableness, or otherwise
of the service charges as a whole to go on
the service charge account from which
no doubt you can assess the proportion for
that particular tenant " .
This clearly demonstrates that the LVT views
the calculation of the service charges
payable by individual lessees as being based
on a fixed
global sum to which the relevant fixed percentage
share is applied - as the norm/
understands the terms of the lease
as such - which
indeed it is.
Mr Gallagher knew full well from the 28 October
2003 meeting with my surveyor, as well as documents
he had been provided with, that Steel Services
had not implemented the LVT
determination. Hence, Mr Gallagher held
against me the fact I had obeyed the instructions
given to me by the tribunal at the 29
October 2002 pre-trial hearing to not
pay the service charge demanded until
it had issued its determination and it had
therefore been implemented).
Yet again, in my 9 August 2003 letter to the
judge, I emphasise the findings from the LVT
determination - and the fact they have not been
implemented.
16 - 19 August 2003

|
I write
a letter I send to all the major
newspapers (e.g. The
Guardian ), as well as Newsnight
(BBC2), the BBC Radio 4 programmes 'You
and Yours' and 'Face the facts',
Private Eye, etc.
A dozen letters in total. Every
time I supply a substantial number
of enclosures in support of my
claim. |
Two or three show some initial interest but,
in the end, only one, the Sunday
Telegraph , pursues the story in its 19
October 2003 issue, heading it "My property nightmare - Extortionate
service charges" . Generally, it seems
to me that the majority of journalists want 'easy
stories', those that do not require time to
understand and can be encapsulated into little
bite size.
Landlord-tenant disputes do not fall into this
category as, while the root cause which seems
to me to be pretty consistent across the board
is very straightforward to understand: ' rip-off ',
the details of the case can be voluminous and
consequently appear to be complex. Only an investigative
journalist of the calibre of Anthea Messy who
wrote the Sunday
Telegraph article, has the competence
to treat this kind of story (very clearly,
she invested the time to ensure she understood
the details of the case).
In addition to the 'multi-event' nature of landlord-tenant
disputes which require time to understand, I
suggest that conflict of interest is likely to
be another factor that prevents reporting of
cases such as mine in some media. Newspapers
that generate significant advertising revenues
from property developers are, I venture, less
likely to run stories that risk killing the 'golden
goose'. Likewise with newspapers that generate
significant revenue from legal appointments ads
by the private and government sector, etc.
Furthermore, for some media I am guessing that
there are probably concerns that an attack on
the leasehold system amounts to, in effect, attacking
the very core of the British establishment given
the profile of the biggest freehold owners in
the U.K. - and they do not want to find themselves
in a 'difficult situation' for the sake of highlighting
the terrible misery suffered by 'nobodies' such
as myself. However, to be fair, some of the more 'enlightened'
press does occasionally write quite critical
(and justly so) articles on leasehold-related
matters.
With every letter I send to the media, I also
copy several ministers - including
the Prime Minister . (In my
introduction to the site I state that "nobody
can plead ignorance' of my case, nor of my
views". You see what I mean).
It seems that the various departments forward
my letter to Mr
John Prescott's Office. It includes,
for example, my letter to the Home Office as
evidenced by the 27
August 2003 reply. (Note that in my letter
I refer to events with Kensington & Chelsea
police. Evidently, the Home Office does not
consider that this matter comes into its court.
Interesting!).
26 August 2003 - The farsical West London County Court hearing
A hearing takes on 26
August 2003 following a 6
August 2003 application, signed by Ms
Ayesha Salim - under a Statement
of Truth - "We CKFT
intend to apply for an Order that (1) There
be Judgement for the Claimant against the
Second Defendant and Fifth Defendant...(2)
The Defendants do pay the Claimant's costs
of those proceedings - Because The Claimant
believes that the Second (and Fifth) Defendants
have no real prospects of successfully defending
the Claim and the Claimant knows of no other
compelling reason why the case should be
disposed of at Trial"
It also states that "Following the decision
on 24th June 2003, MRJ issued a revised
Major Work Apportionment setting out the revised
estimate for the works and calculation
of the percentages due from each of the tenants"
This is not true as, among
others, the documents include a " Major
works apportionment 24th June 2002 revised " issued
by Martin Russell Jones. Compared to
the version issued for the 24
June 2003 hearing, this one lists all
the flats. In each instance, the sum
demanded has been revised down by 24.19%
i.e. the
same amount as for the 24
June 2003 hearing (a document
which had been handed to me by Mr
Silverstone, CKFT, at the 24 June 2003
hearing - with
no supporting evidence ). The
only difference is that in this instance
the document covers the 35 flats
(which was the total number of flats at
the time).
Consequently, given the blatantly obvious (supported
by my surveyor's assessment of 31
July 2003) that the LVT determination
had not been reflected in
the document produced for the 24
June 2003 hearing (and, in any case,
a Section 20 Notice had not been issued
following the determination), it follows
that what Ms
Salim's claim - under a
Statement of Truth - IS
NOT TRUE.
(And it is not the only false
claim made by Ms Salim - under a Statement
of Truth - in her 6 August 2003 application
to the court - see CKFT)

|
The
judge did not
challenge Ms Salim on the claims contained
in the 6
August 2003 application.
This is in spite of my 22
June 2003 , 15
July 2003 and 9
August 2003 letters
in which I related the main
points of the LVT determination - and
to the latter, attached,
among others, a copy of my 31
July 2003 surveyor's
assessment of the LVT determination - which
clearly demonstrates that
the LVT determination has
not been implemented.
In other words: I might
as well have been writing in
invisible ink. |
As I had found the 24 June 2003 hearing experience
quite harrowing due to my lack of knowledge and
experience, for this hearing, I opted to appoint
Piper Smith Basham to represent me.
In my 21
August 2003 letter to Ms McLean, I had
made it very clear that I was not prepared
to 'strike a deal' with Mr Ladsky et.
al.
" About CKFT's offer "to discuss" with
them i.e. try to strike a deal. I am
not prepared to do this. This would be a very
unwise move as it would allow them to get away
with the need to redraw the specification,
thereby leaving me exposed to further demands
at a later stage which, I can guarantee, would
be made (letters from MRJ of 26
March 2002 and 15
July 2002 ).
I also added " By forcing them to do this,
it will put a line under the costs i.e.
they will not have any comeback and,
if they do come back, I will be in a much better
position to challenge them. Last but not least,
I am also hoping that by doing this they
will give up on the block as I am taking away
their opportunity to illegally charge works
to the residents " (How
naïve of me! This scam had been in the
making for years)

|
Prior
to seeing the judge, a conversation
took place between Ms McLean, counsel
and Ms Salim (I did not join this
conversation).
Given my position, it resulted
in 'an understanding' to get me
to pay the costs I had recognised
in my 9
August 2003 letter to the
court. (NB: Although note that
the demand was in breach of the
terms of my lease). |
During the meeting with the judge, Ms Salim's
explanation for the fact that her application
referred to the full amount when, in fact, now,
the sum proposed was less than what she claimed
in her application, she replied: "it was
a clerical error" . And this was
accepted by the judge without the blink of an
eyelid.
At the hearing, I agreed
to pay the sum of £2,255 (US$4,000) ( 26
August 2003 order). Yet, I did
not owe a single penny because
the demand was not compliant with the terms
of my lease as it was not supported by certified
accounts - as I had stated in my defence
to the claim. In addition, it was in breach
of statutory requirements defined under sections
20 and 21 of the Landlord & Tenant Act
1985.
Indeed, not only was the 15 July 2002 demand
not a Section 20 Notice, following the LVT determination
Steel Services-Martin Russell Jones has not issued
a Section 20 Notice .

|
What
prompted me to agree to this payment
were:
(1) the realisation
that fair and just treatment of
the case was evidently not on West
London County Court's agenda - and
that the dice were, in my view,
heavily loaded in favour of Steel
Services;
(2) I had been
told by my solicitor and barrister 'acting
for me' on the day that, if I did
not make a payment, it would be
likely to be held against me. I
believed them.
Yet, this very action was highlighted
by Mr
Gallagher as a factor that
worked against me "consider
the fact that. summary judgement
had already been entered on part
of the claim" (point 66, 9
June 2004 ) |
27 August 2003 - 22h45
As I return from work at 22h45 and I am about
30 metres from the main door to the block, I
pass Mr Ladsky on the pavement.
He is accompanied by a blond woman. As
I go by, he says to me: " loser! " (I
assume he told his companion that he had won
the previous day in court (26 August 2003). It can be argued that
he did, but lost
on getting his costs . A token of justice
for me!).
31 August 2003 - Around 22h45
Somebody makes very loud, thumping noises with
their feet in the entrance corridor. The
level of noise is such that it is clearly
intentional. The
lift is activated for a long time. I can
only conclude that it is Mr Ladsky. Why
would anybody else do this? In addition,
he knew from my 9
August letter to the Court that I can
hear if noise is made in the entrance
corridor.
4 September 2003
As explained, in my 21
August 2003 letter to Ms McLean, Piper
Smith Basham, I had made it very clear
that I was not prepared to 'strike a
deal' with Mr Ladsky et. al. Well, as can
be seen in her 4
September 2003 letter, she and CKFT
were not giving up on the idea:
"Incidentally (NB !!!) ,
I took a call from CKFT today and, in view
of the costs being incurred by both sides they
asked whether we would be amenable to any deals (NB
!!!)
I said that I had noted that you had previously
refused to deal with them but in the event
that they wished to make an offer (NB
!!!) I was, as they well know,
obliged to put it to you (NB !!!)
They intimated that they will make a Part
36 offer (NB !!!) The
relevance of this is that if they make an offer
which is rejected and, following trial the
judge makes a determination that is no better
than the offer that they had made then you
will have to pay their costs from the time
the part 36 offer had been made up until the
trial" (NB Please note
the threat)
Note the "incidentally" . This made
it the second time in the space of three days
that Ms McLean was trying to push me into making
a deal with Mr Ladsky et. al.
I reply as follows on 9
September 2003