
July 2002 -
Photograph of the back of Jefferson House -
at the time that Ms Hathaway, Martin
Russell Jones, sent the £736,000 (US$1.3 million)
service charge demand for the major works |

6 February
2005 - The
scaffolding covers the whole of the facade
of the back of Jefferson House |

6 February
2005 -
Photograph shows that an extra floor is under
construction. (Particularly evident
when comparing the level at which the works
are taking place - against the building on
the left v. the photograph
taken in July 2002) |

2 May 2005 - The
whole area of the back of the block is still
blocked out by scaffolding. As before, a small
crane can be seen on the roof. |

5 June 2005 -
Same state as one month ago: the scaffolding
covers all of the back of the building. The
small crane is still on the roof. |

3 July 2005 -
No change for, yet again, another month: all of the
scaffolding is still in place, and so is the small
crane on the roof |